BCM 345 Presentation
Transcript: Construction Schedule General Requirements April - June Preplanning Order material Soil reports etc Earthwork June - July Foundation excavation Concrete July - December Foundation Footings Foundation walls Slab Erect Steel Frame December Columns Roof Masonry January - February Block walls Brick veneer Doors, windows, and insulation February - March Simulatenous Finishes March - May Drywall Flooring Mechanical/Electrical May - June Simultaneous Exterior July Landscaping Paving Completion August Punchlist Testing •Construction Schedule •Site Plans •Sequence of Construction •Potential problems and solutions •Quality control/ Safety issues •Crews/Equipment Needed •Material Storage Site Plans (cont.) Excessive rain Uncover unmarked utilities Concrete does not meet specified strength Improper fit of steel frame Rain before skylights are installed Delayed delivery of steel trees or sky lights Concrete floor not level to specifications Safety Issues Quality Control Slab Logistics Erosion Control Site Plans (cont.) Conclusion. Matt Hayes, Alex Van Allen, Hillary Kaub, and Clark Cord Site Plans (cont.) Potential Problems Crews and Equipment Structural Framing Problems Proposed solutions Building Envelope Site Plans Storage and Materials Site Construction (Div. 2) Earthwork, utility services Concrete (Div. 3) Concrete forms/rebar, cast-in-place concrete Masonry (Div. 4) Mix veneer mortar, clean brick Metals (Div. 5) Structural steel framing, interior walls Thermal & Moisture Protection (Div. 7) Interior/exterior insulation, spray waterproofing, roofing membrane Doors & Windows (Div. 8) Doors, hardware, windows, trim Quality Control Ensure finished concrete floor is flat to specifications Check sound insulation of acoustical wall systems Have a check-in sheet for all subcontractors to sign to monitor workers on site Monitor task completions and update schedule to make sure project completion date is acheived Installing skylights Installing steel trees Provide fall protection for mezzanine level Have a sign-in sheet for all visitors Put up fencing to keep university students away from hazardous construction Make sure everyone is wearing their personal protection equipment Lay gravel Fix any damaged utilities and research for additional unmarked utilities Could lay an extra layer for added strength Use a cutting torch to fit bolts Cover up skylights Continue work in other areas, condense schedule or utilize overtime if needed Continue to polish Outline Clemson Lee Hall Expansion III Clemson University Sequence of Construction (by CSI division) Interiors Finishes (Div. 9) Drywall, paint, install tile, acoustical insulation Specialties (Div. 10) Fire alarms, fire extinguishers Equipment (Div. 11) Visual display boards, audio/video equipment Conveying Systems (Div. 12) Erect masonry scaffold Mechanical (Div. 15) HVAC, connect water main, plumbing fixtures Electrical (Div. 16) Wall/ceiling wiring, data receptacles, panelboard Foundation Site Plan Safety Issues Start: April 23, 2012 Finish: August 6, 2013 Solutions Any questions?