Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Make your likes visible on Facebook?

Connect your Facebook account to Prezi and let your likes appear on your timeline.
You can change this under Settings & Account at any time.

No, thanks

Copy of STUDY OF FACTORS AFFECTING ON DELAY IN CONSTRUCTION PROJECT

No description
by

ziera anwar

on 14 December 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Copy of STUDY OF FACTORS AFFECTING ON DELAY IN CONSTRUCTION PROJECT

FONTS
Introduction

Delay-
Types of Delays-
Excusable delay with compensation
Excusable Delay without compensation
Non-excusable delay
Scope of Study-
This project give a clear and precise understanding of delay in construction projects especially the factor of causing delay .
Type and effect of delay in construction project will be review and discuss
It also reviews suggestion to reduce the delay problems.
GROUP MEMBERS
1.NURUL HAZIRAH BINTI ANWAR
2.SITI ZULAIKHA BINTI DZAKARIA
3.SITI NOORAINI BINTI TARASENANI
4.AWANG MUHAMAD AYAHTULLAH BIN AWANG NAJERI
GUIDED BY
Mohd Ali Jelani (Assoc. Prof. Ir. Hj.)

Act or event which extends required time to perform work of the contract manifests itself as additional days of work.

Construction delay-

The time over run beyond completion date specified in a Project.

Objectives-
Study the concept of delay
Determine the factors causing delay
Analysis and result of collected data
Determine factors through case study
Give suggestion and recommendation
Methodology-
Step One: Literature Review

Step Two: Interviews and Survey Results Analysis

Step Three: Case Study

Step Four: Conclusions and Suggestions

Factors causing delay-
1. Internal factor
Causes of Delay by Owner
Causes of Delay by Contractor
Causes of Delay by Cost overruns
Causes of Delay by Materials
Causes of Delay by Equipment
Causes of Delay by Labors
2. External factors
1.Delay Caused by Owner
According to most of the researchers the client related factors causing delay are-
Slow decision making of owner
poor communication and coordination by owner and other parties
Interference by the owner in construction operations

2.Delay Due to Contractor
According to most of the researchers the contractor related factors causing delay are-
Inadequate contractors experience
Problems with sub contractor
Ineffective planning & scheduling project
Mistakes during construction
Poor site management and supervision
3.Delay Caused by Cost Overruns
Cost Overruns can arise from events such as-
Cost of energy supply for construction , transportation cost, labor cost, material cost etc.
Financing is also required for
1.Payment of completed work
2.poor contract management
3.changes in site condition
4.storage of materials
5.Improper planning.
4.Material related factors-
According to the most of the researchers the material related factors causing delay are-
Storage of construction materials in market.
Changes in material type & specification during construction.
Escalation of material prices
Delay in material delivery.
Poor quality of material used in construction.
Late in selection of finishing materials
5. Equipment related factors
According to the most of the researchers the material related factors causing delay are-

Unavailability of equipments required for construction.

Limited time available for the allotted equipment.

Equipment breakdown.

Improper working of equipment.

Shortage of power required for operating various equipment.

Low efficiency of the equipment.

6. Labour related factors-
According to the most of the researchers the material related factors causing delay are-

Inadequate labour supply.

Presence of unskilled labors.

Inadequate experience of labour.

Absenteeism.

Slow mobilization and low productivity of labour
7. External factors-
If the site is located in the mountains or valleys, coastal areas etc.

If there are worst whether conditions as snowfall, heavy rains.

Insolvency and Politics.

Delay on site clearance work, Unforeseen soil & weather conditions.

Site related legal problems.

Effects of Delay

Overtime

Disputes

Over cost

Unstable mind

Negotiations

ABANDONMENT
Data collection

Primary data –
Collected from books, journal papers, internet etc.
Secondary data –
field study
Survey Process

Data Analysis and Result

1.Using mathematical tools:

Frequency Analysis
Frequency analysis will be using tabular form to represent result of data analysis of frequency.

Average Index Analysis
Use for determine overall level of importance and evaluation

Table: The level of importance and evaluation for Average Index Analysis

Analysis Of Factors Causing Delay:

About Owner

About Architect

About Consultant

About Engineer

About Contractor

Case study-
The case study was done to find out various factors causing delay related to different field of operation by various personnel's.

The factors, percentage & their importance represented graphically.

Tables consist frequency, relative index, Average index & ranking.

Case study is a phenomenon with its real life context.


CASE STUDY
Analysis and result-
Feedback from various personals

Questioner

Tables

Graphs


Conclusion-
The top ten factors that cause delay in construction project in Pune district as perceived by owner, contractors, architect, consultant and engineer were determined.

The top 10 important factors responsible for delay in construction according to the case studies were also determined and their recommendations were given.

Factors responsible for delay in construction.
Factors responsible for delay in construction about material, equipment & labour
Recommendations on How to Overcome Delay

Frequent progress meeting.

Use up to date technology utilization.

Use proper & modern construction equipment.

Use appropriate construction methods.

Effective strategic planning.

Proper material procurement.

Accurate initial cost estimates.

Clear information through communication channels.

Frequent coordination between the parties involved.

Proper emphasis on past experience.

Proper project planning and scheduling.

Complete and proper designing.

Site management & supervision.

Collaborative working in construction.

Compressing construction durations.

CONTD...
References-

A)M.E.Abd El-Razek; H.A. Bassioni, and A.M.Mobarak (2008)“Causes of Delay in Building Construction Projects in Egypt.”

B) Jonathan Jingsheng Shi, S.O. Cheung, David Arditi- January/February (2001), “Construction Delay Computation Method.”

C)AftabHameedMenon,Ismail Abdul Rahman,AdeAsmi Abdul Azis (June 2011), “Preliminary Study On Causative Factor Leading To Construction Cost Overrun.”

D)MostafaE..Shehata, Khaled M.El-Gohary-27 (June 2011), “Towards Improving Construction Labour Productivity And Projects Performance.”

E) FarhadEizakshiri,PaulW.Chan, Margaret Emsley- “Delays, What Delays? A Critical Review Of The Literature On Delays In Construction.”

F) P.A. Koushki, K. AL-RASHID and N.NARTAM (26 JUNE 2003),”Delays And Cost Increases In The Construction Of Private Residential Projects In Kuwait.”

Case study of a project by Abhimanyu Group named Abhimanyu Nagari was undertaken.
The various problems faced by the company during the project were analysed and causes of delays were found out.

DELAY IN CONSTRUCTION PROJECT
Excusable delay with compensation
Happen when the contractor is entitled to an adjustment for increases in cost to the
performance of the contract.

The reason of the delay is because of unexpected situation and not from the Contractor mistakes

This delay can be cause by client’s action or inaction. In the contract, there are certain clause provided to prevent a breach by the client.

eg: Change and Extra work



Excusable delay without compensation
Non-Excusable delay
Excusable delay without compensable as delays where neither the Client nor the Contractor is deemed responsible.

When this delay happen, only a time extension will be warranted since there are no ground of damages.

Therefore, there is no additional money and no additional time being granted to the Contractor

When contractor avoid the contract agreement

This delay is caused by Contractor or Subcontractor or material suppliers and it is not Client’s fault

Client can claim the loss if it is had in the contract agreement.

These delay had to identify by client because they rarely check the schedule of the construction.
Less than 20% of the Project’s Forecasted Deliverable time frame (Minor)

More than 20% of the Project’s Forecasted Deliverable time frame (Major)