Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Make your likes visible on Facebook?

Connect your Facebook account to Prezi and let your likes appear on your timeline.
You can change this under Settings & Account at any time.

No, thanks

Infrastructure Support of DPWH: Plans & Accomplishments

No description
by

joxanne Calubaquib

on 4 September 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Infrastructure Support of DPWH: Plans & Accomplishments

Infrastructure Support of DPWH: Plans & Accomplishments
design by Dóri Sirály for Prezi
The Construction of Tuguegarao City By-Pass Road
Asphalt Overlay of Cagayan Valley Road (Iguig-Amulung Section)
ROADS
THIS SITE
PAVING OF JUNCTION NATIONAL ROAD - BITNONG- BELANCE- NUEVA VIZCAYA ROAD
SIGNIFICANCE
THIS SITE
The Construct ion of Tuguegarao City – By-Pass Road

involves widening the of existing PCCP on both sides, including construction of drainage, curb, gutter and sidewalk along the mainline.
The newly constructed road will serve as an alternate route for commuters plying the north-south and the east-west lateral roads of Tuguegarao City especially those from the southeastern towns of Cagayan Province and Kalinga (Tabuk).
The project when completed shall reduce significantly the traffic congestion and constriction in the city. It will also facilitate coordination and linkage among national government agencies including the provincial government Of Cagayan and city government of Tuguegarao.
TUGUEGARAO CITY BY-PASS ROAD
THIS SITE
Iguig & Amulung, Cagayan
Asphalt Overlay of Cagayan Valley Road (Iguig-Amulung Section)

Original Contract Amount
Php 150,731,937.95

• Overall Status of the Project
(As of March 25, 2014)
Detailed Design - Completed
Pre-Construction - Completed
Construction
Planned 100%
Actual 100%

Implementation Schedule
Start Date April 20, 2012
Original Completion Date October 16, 2012
Revised Completion Date December 15, 2012

II. PROJECT DESCRIPTION
This project involves the construction of Bituminous Concrete Surface Course over a length of 23,600 lin.m. It also includes the removal and replacement of damaged PCC blocks and improvement of the carriageway.


III. PROJECT IMPACT
This road surface treatment will extend the service life of the carriageway specifically at section K0488+000 to K0511+600 of Cagayan Valley Road.

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Benchmark for Upgrading to Paved Road Standard
(HDM-4 Project Analysis) Intermittent Section, Cordon-Diffun-Maddela-Aurora Boundary Road
THIS SITE
Concreting of Access Road Aparri Airport, Maura
Aparri, Cagayan

Original Contract Amt.:
Php 27,645,023.31
Revised Contract Amt.:
Php 28,824.916.41
Scope of Work:
Concreting of Roadway of 1.559 kms length, 6.70m width and thickness of 0.28m;
25 ln.m. 910mm Ø Pipe Culvert ; Grouted Riprap and Stone Masonry
Fund Source:
CY 2013 DPWH Regular Infra
(To Major Airport)
Implementing Office:
DPWH – CFDEO

Concreting of Access Road Aparri Airport, Maura
Status:
Completed
Project Impact:
The concreting of the Access Road opens a great opportunities for traversed barangays for development. This road links the municipalities of Aparri and Buguey both in the Province of Cagayan. Buguey being the “Seafood Bowl” of Cagayan has a great cut on travelling time and cost to businessman selling their produce to Aparri which is the business center of Northeastern of Cagayan.
Students coming from the far flung barangays and studying in various colleges and universities at Aparri are also benefited. Their travel time and cost will be reduced for more than 60% from their usual daily expenses.
The development of this road surely attracts tourist to the different tourist destination in the area which surely brings employment in the countryside.

Concreting of Access Road Aparri Airport, Maura
THIS SITE
Nagtipunan, Quirino
Original Contract Amount: P 66,128,843.39
Revised Contract Amount : 69,130,991.20
Start Date : February 18, 2013
Contract Duration : 237 CD
Revised Contract Duration : 267 CD
Completion Date : October 12, 2013
Revised Completion Date : December 13, 2013
Concreting of 2,880.174 ln.m., 0.23m thick with slope protection. Road Width = 6.7 m.
The upgrading (gravel to paved) of Cordon-Diffun-Maddela-Aurora Boundary Road has a total length 5.040 km. It involves concrete paving and slope protection works.
The road links the province of Quirino to the province of Aurora. When completed, it will facilitate transport of basic goods to the areas, and improve the socio-economic activities and tourism industry.
THIS SITE
Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Benchmark for Upgrading to Paved Road Standard
(HDM-4 Project Analysis) Intermittent Section, Aritao-Quirino Road
Kasibu, Nueva Vizcaya
Original Contract Amount: P 98,679,511.06
Revised Contract Amount : P102,739,454.08
Start Date : February 18, 2013
Contract Duration : 269 CD
Revised Contract Duration : 281 CD
Completion Date : November 13, 2013
Revised Completion Date :December 13, 2013
Concreting of 4,256.249 ln. m. pavement, width 6.70m and Construction of Protection Work &
line canal Sta.272+358.60 to Sta.278+991.48 Thickness = 0.23m
The concrete paving of Aritao-Quirino Road,
Dupax del Norte and Kasibu Sections in Nueva
Vizcaya has a total length of 8.508 km with an
allocation of Php 195,923,000.00. The scope of
work involves concrete paving, bank protection
works (stone masonry) with line canal and widening
of roadway (cutting of side slopes in mountain
areas).
This road section connects Region II provinces
Nueva Vizcaya and Quirino to Region III
particularly the province of Aurora. The project
will provide fast, smooth and convenient travel
and facilitate transport of goods and products
to the influence area that will bring about socioeconomic
development of the region.
Road Upgrading (gravel to paved) Based on gravel road strategies, traffic benchmark for
Upgrading to paved road standard (HDM-4 project analysis) (MFO-2) intermittent sect.
Nueva Vizcaya-Pangasinan Road
THIS SITE
Sta. Fe, Nueva Vizcaya
Concreting of 2.089 ln.m. pavement, width 6.70m and Construction of Protection Work & line canal Sta.224 +250 to Sta.226+920.
Thickness : 0.23 m
Original Contract Amount:P 87,709,817.90
Revised Contract Amount:91,978,861.069
Start Date:February 18, 2013
Contract Duration:110 CD
Revised Contract Duration:327
Completion Date:October 12, 2013
Revised Completion Date:January 13, 2014
Nueva Vizcaya-Pangasinan Road
Nueva Vizcaya-Pangasinan Road
Road Upgrading to paved road standard (HDM-4 project analysis) (MFO-2) intermittent sect.
Jct. Victoria-Maddela-Alicia-Kasibu Boundary Road
THIS SITE
Jct. Victoria-Maddela-Alicia-Kasibu Boundary Road
Maddela, Quirino
Concreting of 6,870.28 ln.m. pavement, width 6.70m and Construction of Protection Work & lined canal
Thickness = 0.23m
Original Contract Amount:P 169,189,556.54
Revised Contract Amount:178,834,616.75
Start Date:February 18, 2013
Contract Duration:330 CD
Revised Contract Duration:420 CD
Completion Date:January 13, 2014
Revised Completion Date:April 13, 2014
Jct. Victoria-Maddela-Alicia-Kasibu Boundary Road
Repair/Rehabilitation/Improvement of Roads from Basco to Imnajbu, Mahatao-
San Vicente-IvanaUyugan Section
THIS SITE
Batan Island, Batanes
Original Contract Amount:P 48,728,614.55
Start Date:November 22, 2013
Contract Duration:360 CD
Completion Date:November 17, 2014
Repair/Rehabilitation/Improvement of Roads from Basco to Imnajbu, Mahatao-San Vicente-IvanaUyugan Section
The concrete paving of Uyugan-Mahatao Interior Road in Basco, Batanes has a total length of 3.004 km. It involves
concrete paving, road widening and slope protection works. When completed, it will serve as a vital
access road to speed-up the delivery of basic goods and services to the neighboring towns, barangays and in the
centers of trade and commerce in Batanes.
THANK YOU!