Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

What is the problem with Paks II?

ENERGIAKLUB
by

ENERGIAKLUB profile

on 14 April 2015

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of What is the problem with Paks II?

Paks I
Nuclear capacity
2.5 billion EUR own funding
10.000
20.000
30.000
40.000
50.000
60.000
0
WHAT
WITH
PAKS II
?
IS
Ada Ámon
Energiaklub, Budapest
19 March 2015
Brussels

ITSELF
IS
THE
PROBLEM
25
years
Fields of activities
Energy efficiency
Climate protection and adaptation
Energy policy
Conventional energy sources
Renewable energies
2009
2010
2011
2012
2013
2014
2015
2009
Parliamentary decision
2009–2013
Lévai project – preparing for tender
January 2014
Agreement in Moscow
The Paks II chronology
2014
2015
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
February 2014
Parliament passes law on framework agreement
June 2014
Parliament passes law on loan agreement
December 2014
3 implementation agreements signed (construction, maintenance, fuel & waste)
3 March 2015
Lex Paks II passed
The Paks II chronology
Paks
What is Paks II?
This is what we know
Total investment:
of the annual
state budget
20%
12.5 billion EUR
What is Paks II?
Repayment of loan starts in 2026
20 years
of fuel supply
2 VVER-1200
type reactors
Spent fuel
to Russia
2
Production forecast of Paks NPP and electricity consumption of Hungary
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
Consumption, MAVIR forecast
Paks I
GWh
Problems with the decision
Centralization
of the decision and the energy system
preliminary investigations, impact assessments
public consultations
transparency
alternative scenarios
Problems from EU aspects
- Distortions of the market
Risks of corruption
tender
Illegal state aid
Obstacles to renewables
Aarhus Convention Compliance Committe
– on access to information and the decision making process
Impacts
on
Hungary
Risk of illegal party financing
Economic problems: high electricity price or higher tax
Indepted to Russia
Centralised energy system
No alternatives and healthy organic development of the electricity market
Influence of corruption on the social and political system
Disregarding of EU rules
Energy security – dependence on Russia
Political risks
Corruption risk
Distortion of market
Lack of
Lack of
Lack of
Lack of
Lack of
DG Competition
– illegal state aid
Impacts
of Paks II on the EU
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
10.0 billion EUR Russian loan
Production and consumption
2 complaints
by Energiaklub
I believe that this NPP will never be built,
since it does not serve the interest of Hungary and Europe.
Ada Ámon
Energiaklub, Budapest
19 March 2015
Brussels
]
realise,
bring together,
follow up,
distribute,
mediate,
train,
communicate
analyse,
study,
scrutinise,
explain,
examine,
compare,
evaluate,
conceptualise
[think]
[do]
&
Current capacity is
4x500=2000 MW
Planned extra
capacity is
2x1200=2400 MW
2 March 2015
Euratom Supply Agency
2024
33%
of total consumption
Production of Paks NPP
%
2026
66
System load and capacity
Daily gross system load curve (annual average) and nuclear capacity
1.000
2.000
3.000
4.000
5.000
6.000
0
GW
Source: MAVIR, Energiaklub calculations
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Hours
Paks I+II
Daily gross system load curve
2011
2030
Nuclear production
Paks II
pakskontroll.hu/en