Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Make your likes visible on Facebook?

Connect your Facebook account to Prezi and let your likes appear on your timeline.
You can change this under Settings & Account at any time.

No, thanks

Board of Directors Meeting

Enterprise Seaway Segment 1 - Earl Collins, Mike Futch, Scott Timpone.
by

Leah Martinez

on 23 September 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Board of Directors Meeting

Willbros Group, Inc.
Meeting Title
Enterprise Seaway Segment 1

November 20, 2013

Earl Collins
Mike Futch
Scott Timpone

Key Results
Safety
: TRIR < 1; Zero Fatalities
People
: Voluntary Turnover <10%
Customer
: Improved Customer Satisfaction and Key Client Connectivity
Cash
: DSO < 60 Days
Operating Income
: 3.2% moving to 5.2%
Seaway Segment 1
Date bid was solicited................Jun-17-13
Bid due date original.................Jul-12-13
Extension...................................Jul-15-13
Award date.................................Jul-22-13
Contract signed..........................Aug-02-13
Takeoffs........................16 hours (1 person)
Estimate......................184 hours (1 person)
Subcontract...................90 hours (1 person)


Total man hours = 290

Project Controls
• Original budgets set up per estimate
• Monthly Cost Report (MCR) created and is being
maintained by Project Controls
• Daily Progress Report - Man hours/progress to date
• Weekly Construction Report - Overall synopsis
• Subcontract log
• Tilos™ schedule/progress setup and maintained by Project Controls
Project Execution
Safety

336,000
man hours with
zero
OSHA recordable
incidents

• Took accountability for line strike incidents

• Meeting with Enterprise on regular basis

Line Strikes
• Involved lines through two large old oil fields that were not identified
on the drawings or by one call and in most cases were polyurethane
lines without tracer wires and abandoned

• Ground disturbance process not properly followed

• Added new locators and process assurance measures

• Engaged Premier to review USC ground disturbance/line locating
processes

Blasting
Coating
Plasma Cutting
• Willbros is currently one of two contractors to use
plasma technology in mainline pipeline construction

• Willbros uses Barracuda Cutting Systems, which is a diesel-powered mobile
plasma cutter
- The system saves both time and money
by eliminating 99% of
Oxyfuel. The technology also leaves a slick non-slag bevel, which
decreases grinding and in-turn provides a safer work environment.

• Twice as fast with increased safety
Automatic Welding
PMO

Measuring
- Time to distance march chart
- Productivity analysis
- Resource loading analysis


Monitoring
- Adjustments to current budget
+ Actual progress
+ Estimated schedule
- Contingency management
- Change management
+ Request information (RFI) process
+ Change log
• Safety

• Customers

Delivering Our Key Results:
Big Inch, Cross Country Pipeline
How we will do business:
• People

• Cash

• Willbros has no recent history in trench blasting

• Recognized as a risk during bidding phase

• Partnered with Dykon, a leading
expert in the field. Developed
blasting plan with Senior
Superintendent, Randy Dolin.

• Mitigated risk, maintained
schedule without incident
• Operating Income
A Good Job On Time... Done Right!
Moving Forward
Through Consistent and Predictable Performance