In 1992, Al-Mubarkia begin as a general works contractor then the company quickly expand into residential and remodeling projects it’s locate in shweikh industrial
Our employee have the opportunity to develop and the freedom to make decisions. We also train our staff to be equipped for work and life in 21st century. Our goal is simple we want every worker to go home safety to their families every night..
We estimate the project duration which was 180 days ( 6 months) and the cost is 970282.1205 KD.
Direct cost = 8472.13 + 2945 + 3037.4 + 2232 + 800 + 199591.68 + 671000 = 888078.21 KD
Indirect=(6000) x (6)=36000 KD
Total cost=888078.21+36000= 924078.21 KD
Profit=(5%) x (924078.21)=46203.9105 KD
Total bid cost = 924078.21 + 46203.9105 = 970282.1205 KD
- Our company
- Project description
- Project organization
- Construction methodology
- Conclusion
Kuwait University
College of Engineering & Petroleum
Civil Engineering Department
Alanood Thani Al-Shammeri 2121111128
Ahlam Al-Otaibi 2121114947
Maryam Al-daraawi 2121113179
Construction Estimation and Cost Control
CE 434
SIX-STORY OFFICE BUILDING PROJECT
Dr. Anwar Al-ibrahim
- Consist of super structural ( Structural Steel ) & substructure ( earth work and concrete work)
- The total area of the project from the attached drawings equal to 50m x 25m.
- Project planned to start at January 1, 2017 and finish at Jun 30, 2017.