1. Improve the water quality of the effluent discharged into the North Platte River
2. Design a highly operable WWTP
3. Reach stakeholder consensus by meeting all client and public requirements
4. Decrease the quantity of residual solids within treatment processes, and sufficiently treat the remaining solids to be recycled or safety disposed
5. Design a low-cost and high-benefit solution that achieves all other goals
Ben Collamer, HCH Engineering Owner & Design Engineer
Britton Hammit, Project Manager
Josh Harkins, Lead Engineer
Recommendations:
Lift Station and Pump
HCH Engineering: hcheng@hch.com
307-710-8668
Ben Collamer: bcollame@uwyo.edu
Britton Hammit: bhammit1@uwyo.edu
Josh Harkins: jharkin2@uwyo.edu
Vortex Grit Chamber
1. Evaluate current operations at Torrington WWTP
2. Identify alternatives to meet future regulations
3. Compare alternatives
4. Provide a final recommendation with design details
Lagoon System
SAGR
Backwash Gravity Sand Filter (1)
Backwash Gravity Sand Filter (2)
UV Disinfection
Finishing Pond for Flow Regulation
Cascade Aeration and Discharge to North Platte River
BOD Score Calculation
(100%-98.5%)
__________
= 0.14
*(0.15)
(100%-85%)