Manpower Planning Cont.
Flexible Pipelines (2.5 km per line) - May - June 2017 (QC-TBA)
Mattress Installation - July - August 2016 (QC - Nazri/Amar)
BNCPP Jacket Dimensional Survey at MMHE - January 2016 (QC - Nazri/Dian/Azan)
Manpower Planning
Geomatics Involvement
1. Integrated anchor pattern for SIMOPS
2. Technical support
3. QA/QC on survey positioning during
installation campaign
Geoinfo
Pipeline Installation
TTJT-A to BNCPP-B (24" x 43 km)
1. Pre Lay Survey - February 2016 (QC - Amar)
2. Installation - Mid March - Mid April 2016 (QC - Bagus)
3. Riser at TTJT-A - May 2016 (QC - RPS)
4. Post Lay Survey - May 2016 (QC - Dian)
5. Riser at BNCPP - April 2017
BNCPP-B to E11RC (24" x 124 km)
1. Pre Lay Survey - March 2016 (QC - Amar/Dian)
2. Installation - May - End July 2016 (QC - Harun/Nazri/Dian/Amar )
3. Riser at E11R-C - August 2016 (QC - Azan)
4. Post Lay Survey - August 2016 (QC - Bagus )
5. Riser at BNCPP - April 2017 (QC - TBC)
Platform Installation
TTJT-A
1. Debris Survey - March 2016 (QC-Amar)
2. Jacket - April 2016 (QC - RPS)
3. Topside - May 2016 (QC - Amar)
BNCPP-B
1. Debris Survey - February 2017 (QC -TBC)
2. Jacket - March 2017 (QC -TBC)
3. Bridge - April 2017 (QC -TBC)
4. Topside - May 2017 (QC -TBC)
BNJT-K
1. Debris Survey - February 2017 (QC -TBC)
2. Jacket - March 2017 (QC -TBC)
3. Bridge - April 2017 (QC -TBC)
4. Topside - April 2017 (QC -TBC)
Geohazards
Operations
What is BARDEGG
Project Information
1. The BARDEGG-2 & Baronia EOR development project's offshore campaign in 2016 & 2017 will involve multiple contractors (Wells, Installation,HUC) with very high vessel movement within the Baronia complex vicinity.
2. Located at Sarawak water / SKO Miri
3. Water depth is 75m
4. CRS 1: Timbalai 1948/BRSO (ft) (EPSG:29872) (Installation - Pipelines/Structure)
5. CRS 2: WGS 84/UTM 49N (EPSG:32649) (Integrated Anchor Pattern)
Project Development
Greenfield Development
Brownfield Modifications
Rigid Pipelines
Flexible Pipelines (2.5 km per line)
Submarine Composite Cable
Baronia Rejuvenation Project
Project Schedule
Challenges & Mitigations
1. Survey procedure and selection of survey equipment to meet engineering/installation tolerance.
2. CRS for SIMOPS
3. IMCA standard protocol for inter-vessel data telemetry
4. Congested pipelines and subsea structures facilities
5. Long pipeline installation by anchor barge
Presenter :
Mohd Nazri B Masrom
M Amaruddin Azman
Geomatics Operations PCSB
Geomatics Initiatives
1. GIS based project envelope
Geomatics to propose operations dashboard that will add value to PMT project monitoring such as:
2. Early engagement with various engineering discipline team eg. DCI, pipelines, structures etc.
3. Verify all the informations in AFC drawings (existing pipelines/structures) prior to installation