Manpower Planning Cont.

Flexible Pipelines (2.5 km per line) - May - June 2017 (QC-TBA)

  • Water Injection line from BNCPP-B to BNJT-K
  • Gas Injection line from BNCPP-B to BNJT-K
  • Produced Water line from BNJT-K to BNCPP-B
  • FWS NAG from BNJT-K to BNCPP-B

Mattress Installation - July - August 2016 (QC - Nazri/Amar)

BNCPP Jacket Dimensional Survey at MMHE - January 2016 (QC - Nazri/Dian/Azan)

BARDEGG-2 & BARONIA PROJECT

Manpower Planning

Geomatics Involvement

1. Integrated anchor pattern for SIMOPS

2. Technical support

3. QA/QC on survey positioning during

installation campaign

Geoinfo

Pipeline Installation

TTJT-A to BNCPP-B (24" x 43 km)

1. Pre Lay Survey - February 2016 (QC - Amar)

2. Installation - Mid March - Mid April 2016 (QC - Bagus)

3. Riser at TTJT-A - May 2016 (QC - RPS)

4. Post Lay Survey - May 2016 (QC - Dian)

5. Riser at BNCPP - April 2017

BNCPP-B to E11RC (24" x 124 km)

1. Pre Lay Survey - March 2016 (QC - Amar/Dian)

2. Installation - May - End July 2016 (QC - Harun/Nazri/Dian/Amar )

3. Riser at E11R-C - August 2016 (QC - Azan)

4. Post Lay Survey - August 2016 (QC - Bagus )

5. Riser at BNCPP - April 2017 (QC - TBC)

Platform Installation

TTJT-A

1. Debris Survey - March 2016 (QC-Amar)

2. Jacket - April 2016 (QC - RPS)

3. Topside - May 2016 (QC - Amar)

BNCPP-B

1. Debris Survey - February 2017 (QC -TBC)

2. Jacket - March 2017 (QC -TBC)

3. Bridge - April 2017 (QC -TBC)

4. Topside - May 2017 (QC -TBC)

BNJT-K

1. Debris Survey - February 2017 (QC -TBC)

2. Jacket - March 2017 (QC -TBC)

3. Bridge - April 2017 (QC -TBC)

4. Topside - April 2017 (QC -TBC)

Geohazards

Operations

What is BARDEGG

Project Information

1. The BARDEGG-2 & Baronia EOR development project's offshore campaign in 2016 & 2017 will involve multiple contractors (Wells, Installation,HUC) with very high vessel movement within the Baronia complex vicinity.

2. Located at Sarawak water / SKO Miri

3. Water depth is 75m

4. CRS 1: Timbalai 1948/BRSO (ft) (EPSG:29872) (Installation - Pipelines/Structure)

5. CRS 2: WGS 84/UTM 49N (EPSG:32649) (Integrated Anchor Pattern)

Project Development

Greenfield Development

  • A Central Processing Platfrom (BNCPP-B) bridge-linked to BNG-B
  • A wellhead platfrom (BNJT-K) bridge-linked to BNDP-I
  • A wellhead platfrom (TTJT-A)

Brownfield Modifications

  • Baronia Complex-A and Complex-B
  • E11R-C Host Tie-in

Rigid Pipelines

  • TTJT-A to BNCPP-B (24" x 43 km)
  • BNCPP-B to E11RC (24" x 124 km)

Flexible Pipelines (2.5 km per line)

  • Water Injection line from BNCPP-B to BNJT-K
  • Gas Injection line from BNCPP-B to BNJT-K
  • Produced Water line from BNJT-K to BNCPP-B
  • FWS NAG from BNJT-K to BNCPP-B

Submarine Composite Cable

  • BNCPP-B to BNJT-K

Baronia Rejuvenation Project

  • 14 existing platfroms (excl. BNV-B and BNJT-H platforms which have been identified for decommissioning)

Project Schedule

Challenges & Mitigations

1. Survey procedure and selection of survey equipment to meet engineering/installation tolerance.

2. CRS for SIMOPS

3. IMCA standard protocol for inter-vessel data telemetry

4. Congested pipelines and subsea structures facilities

5. Long pipeline installation by anchor barge

Presenter :

Mohd Nazri B Masrom

M Amaruddin Azman

Geomatics Operations PCSB

Geomatics Initiatives

1. GIS based project envelope

Geomatics to propose operations dashboard that will add value to PMT project monitoring such as:

  • Monitor activities and events
  • Track project field workforce
  • Assess the status and performance of daily operations.

2. Early engagement with various engineering discipline team eg. DCI, pipelines, structures etc.

3. Verify all the informations in AFC drawings (existing pipelines/structures) prior to installation