1665: Air Tip/ Mini-Kup Seal Lessons Learned
Schedule Delays
Tooling
Samples
In Closing
Project Background
Sample Approval
Scope: 500 pcs.
Planned date: 20-Sept 2016
- continue to improve requirements gathering for customer's testing requirements
- capturing better DFM in RFQ?
- buffering schedules to customers
- be available on Skype!
- Make another round of samples to improve color
- customer feedback on drawings/ PEG/ sample review lagged
- Flash requirements disconnect resulting in single-cavity tool
- Color and shrinkage issues
- Initiated project in 29-Feb 2016
- Lead Time: 8 weeks for tooling. 2 more weeks for sampling. Customer has specific requirements on flashing and other aesthetic features
- Scope: tool-up for two silicone rubber parts: Intake and discharge air supply components for customer's cages. Customer has a desired cut-in 11/2016 date for 1st production
- Manufacturing Process: Compression molding
- EW BU: EWILO
2017
June
2016
PPAP
1st Production FOB
- Project required Level III PPAP;