HOUSING IBC OF MACHINING -

...............

ENG. EDGAR GARCÍA

ENG. JAVIER HERNÁNDEZ

**FEASIBILITY ANALYSIS**

18-AUGUST-2023

1ST PROPOSAL

MACHINES PROPERTY OF ZF

TRANSMECANICA

ZF FRIEDRICHSHAFEN AG

MACHINES (PROPERTY OF ZF)

EQUIPMENT / MACHINE CONSUMABLES

EQUIPMENT INSURANCE

1ST PROPOSAL

MAINTENANCE OF EQUIPMENT / MACHINES.

TOOLINGS FOR MACHINE.

PACKING

RELEASE OF COMPONENTS WITH CMM

MATERIAL

HUMAN CAPITAL

ANODIZED

INCOMTERMS: EXW

PROCESS

CYCLE TIME OF PIECE

CURRENT CYCLE TIME: 5 MINUTES PER PIECE.

FOR THE 1,200,000 COMPONENTS REQUIREMENT PER YEAR, 15 MACHINES WITH 4 SPINDLES ARE REQUIRED FOR ONLY 1 PART NUMBER.

ACCORDING TO THE FOLLOWING VARIANTS:

-8 HOUR SHIFTS = 96 PIECES

-6 DAYS A WEEK = 1,728 PIECES

-48 WORKING WEEKS = 82,944

CONSIDERING THIS AMOUNT TRANSMECANICA EVEREST REQUIRED 15 MACHINES WITH 4 SPINDLES TO REACH THIS MENTIONED VOLUME .

ESTIMATE START

STARTING AFTER THE PURCHASE ORDER

PROTOTYPES MANAGEMENT

MASS PRODUCTION MANAGEMENT

ESTIMATE TIME

AFTER THE PURCHASE ORDER 6-8 WEEKS.

AFTER THE PURCHASE ORDER 2-3 MONTHS.

-THE TIMES OF THIS PLANNING MAY BE SUBJECT TO CHANGES BY ZF AS WELL AS THE STARTING DATES.

-WORK IS GOING TO BE WITH A RAMP-UP SYSTEM TO KNOW THE REQUIREMENTS FOR THIS PROJECT.

2ND PROPOSAL

INVESTMENT 50/50

ZF & TRANSMECANICA

THE TWO ORGANIZATIONS WILL INVEST IN THE MACHINERY, MANUFACTURING AND MEASURING EQUIPMENT.

TRANSMECANICA

ZF FRIEDRICHSHAFEN AG

2ND PROPOSAL

HUMAN CAPITAL

MATERIAL

INFRAESTRUCTURE

CLAMPING TOOLS

PACKING

INCOMTERMS: EXW

ANODIZED

CONSUMABLES AND EQUIPMENT MAINTENANCE

ESTIMATE

START

ESTIMATE START

STARTING AFTER RECEIVING THE PURCHASE ORDER

MASS PRODUCTION MANAGEMENT

PROTOTYPE MANAGEMENT

AFTER THE PURCHASE ORDER 6-8 WEEKS.

AFTER THE PURCHASE ORDER 9-11 MONTHS.

-THE TIMES OF THIS PLANNING MAY BE SUBJECT TO CHANGES BY THE CLIENT, AS WELL AS THE STARTING DATES.

-WORK IS BEING ON A RAM-UP SYSTEM TO MEET THE REQUIREMENTS OF THIS PROJECT.

-TRANSMECANICA EVEREST ALREADY HAVE IMPROVEMENTS IN THE KNOW HOW IN COMPARE WITH ZF.

PROCESS

CYCLE TIME OF PIECE

OPERATION 10

OPERATION 20

CURRENT TARGET 2.40 MINUTES PER PIECE.

CURRENT TARGET 6.2 MINUTES FOR 2 PIECES

FOR THE REQUIREMENT OF 1,200,000 COMPONENTS PER YEAR, 9 MACHINES WITH 4 SPINDLES ARE REQUIRED FOR ONE PART NUMBER.

ACCORDING TO THE FOLLOWING VARIANTS

FOR THE REQUIREMENT OF 1,200,000 COMPONENTS PER YEAR, 9 MACHINES WITH 2 SPINDLES ARE REQUIRED FOR ONE PART NUMBER.

ACCORDING TO THE FOLLOWING VARIANTS

IMPROVEMENT

86.81%

-8 HOUR SHIFTS = 155 PIECES

-6 DAYS A WEEK = 2,790 PIECES

-48 WORKING WEEKS = 133,920 PIECES

-8 HOUR SHIFTS = 166 PIECES

-6 DAYS A WEEK = 3,000 PIECES

-48 WORKING WEEKS = 144,000 PIECES

FOR THIS AMOUNT TRANSMECANICA EVEREST REQUIRED 9 MACHINES WITH 2 SPINDLES TO REACH THE VOLUME EXPOSED.

FOR THIS AMOUNT TRANSMECANICA EVEREST REQUIRED 9 MACHINES WITH 4 SPINDLES TO REACH THE VOLUME EXPOSED.

ESTIMATED

INVESTMENT

ESTIMATE INVESTMENT

TOTAL INVESTMENT

GOAL

2024

$50M USD

100%

658,168

MACHINERY PRODUCTION LINE TIME & PIECES DELIVERIES RAMP-UP

SEPTEMBER

2024

90%

¡PIECES !

AUGUST

2024

68.5%

1 MACHINES WITH 4 SPINDLES AND 1 WITH 2 SPINDLES = 144,000 FINISHED PIECES

46%

JULY

2024

2 MACHINES WITH 4 SPINDLES AND 2 WITH 2 SPINDLES = 288,000 FINISHED PIECES

JUNE

2024

22.5%

MAY

2024

2 MACHINES WITH 4 SPINDLES AND 2 MACHINES WITH 2 SPINDLES = 288,000 FINISHED PIECES

2 MACHINES WITH 4 SPINDLES AND 2 WITH 2 SPINDLES = 288,000 FINISHED PIECES

2 MACHINES WITH 4 SPINDLES AND 2 MACHINES WITH 2 SPINDLES = 288,000 FINISHED PIECES

TOTAL 1,200,000 PIECES

NOTE: INFORMATIONAL PURPOSES ONLY

3RD PROPOSAL

TRANSMECANICA

100% MACHINING SERVICE INVESTMENT

TRANSMECANICA

ZF FRIEDRICHSHAFEN AG

3RD PROPOSAL

ZF:

-MATERIAL

-PACKING

-ANODIZED

-MACHINES.

-CMM MACHINES.

-INFRAESTRUCTURE.

-INCOMTERMS: EXW

-EQUIPMENT INSURANCE.

ESTIMATED

INVESTMENT

ESTIMATE

START

ESTIMATE START

STARTING AFTER RECEIVING THE PURCHASE ORDER

PROTOTYPE MANAGEMENT

MASS PRODUCTION MANAGEMENT

AFTER THE PURCHASE ORDER 6-8 WEEKS.

AFTER THE PURCHASE ORDER 9-11 MONTHS.

-THE TIMES OF THIS PLANNING MAY BE SUBJECT TO CHANGES BY THE CLIENT, AS WELL AS THE STARTING DATES.

-WORK IS BEING ON A RAM-UP SYSTEM TO MEET THE REQUIREMENTS OF THIS PROJECT.

-TRANSMECANICA EVEREST ALREADY HAVE IMPROVEMENTS IN THE KNOW HOW IN COMPARE WITH ZF.

PROCESS

CYCLE TIME OF PIECE

OPERATION 10

OPERATION 20

CURRENT TARGET 2.40 MINUTES PER PIECE.

CURRENT TARGET 6.2 MINUTES FOR 2 PIECES

FOR THE REQUIREMENT OF 1,200,000 COMPONENTS PER YEAR, 9 MACHINES WITH 4 SPINDLES ARE REQUIRED FOR ONE PART NUMBER.

ACCORDING TO THE FOLLOWING VARIANTS

FOR THE REQUIREMENT OF 1,200,000 COMPONENTS PER YEAR, 9 MACHINES WITH 2 SPINDLES ARE REQUIRED FOR ONE PART NUMBER.

ACCORDING TO THE FOLLOWING VARIANTS

IMPROVEMENT

86.81%

-8 HOUR SHIFTS = 155 PIECES

-6 DAYS A WEEK = 2,790 PIECES

-48 WORKING WEEKS = 133,920 PIECES

-8 HOUR SHIFTS = 166 PIECES

-6 DAYS A WEEK = 3,000 PIECES

-48 WORKING WEEKS = 144,000 PIECES

FOR THIS AMOUNT TRANSMECANICA EVEREST REQUIRED 9 MACHINES WITH 2 SPINDLES TO REACH THE VOLUME EXPOSED.

FOR THIS AMOUNT TRANSMECANICA EVEREST REQUIRED 9 MACHINES WITH 4 SPINDLES TO REACH THE VOLUME EXPOSED.

ESTIMATED

INVESTMENT

ESTIMATE INVESTMENT

TOTAL INVESTMENT

GOAL

2024

$50M USD

100%

658,168

MACHINERY PRODUCTION LINE TIME & PIECES DELIVERIES RAMP-UP

SEPTEMBER

2024

¡PIECES !

90%

AUGUST

2024

68.5%

1 MACHINES WITH 4 SPINDLES AND 1 WITH 2 SPINDLES = 144,000 FINISHED PIECES

46%

JULY

2024

2 MACHINES WITH 4 SPINDLES AND 2 WITH 2 SPINDLES = 288,000 FINISHED PIECES

JUNE

2024

22.5%

MAY

2024

2 MACHINES WITH 4 SPINDLES AND 2 MACHINES WITH 2 SPINDLES = 288,000 FINISHED PIECES

2 MACHINES WITH 4 SPINDLES AND 2 WITH 2 SPINDLES = 288,000 FINISHED PIECES

2 MACHINES WITH 4 SPINDLES AND 2 MACHINES WITH 2 SPINDLES = 288,000 FINISHED PIECES

TOTAL 1,200,000 PIECES

NOTE: INFORMATIONAL PURPOSES ONLY

4TH OPTIONAL PROPOSAL

TRANSMECANICA

IMPROVEMENT IN KNOW HOW

IMPROVEMENTS IN CLIENT'S PROCESS TO INCREASE PRODUCTIVITY AND EFFICIENCY UNDER THE INTELECTUAL PROPERTY OF TRANSMECANICA EVEREST.

IMPLEMENTING THESE IMPROVEMENTS IN THE NUMBER OF ZF MACHINES INITIALLY ASSIGNED TO TRANSMECANICA (LIKE 1ST PROPOSAL) WITH THE CONDITION TO INCREASE IN THE FUTURE THE CAPACITY OF MACHINES FOR THIS 2 COMPONENTS (WITH REFERENCE TO PROPOSAL 2 AND 3).

GETTING 86.81% OF IMPROVEMENT, ALL OF THESE

IMPLEMENTATIONS IN JOINT WITH SW MACHINES SUPPLIER.

4TH PROPOSAL

PROCESS

CYCLE TIME OF PIECE

OPERATION 10

OPERATION 20

CURRENT TARGET 2.40 MINUTES PER PIECE.

CURRENT TARGET 6.2 MINUTES FOR 2 PIECES

FOR THE REQUIREMENT OF 1,200,000 COMPONENTS PER YEAR, 9 MACHINES WITH 4 SPINDLES ARE REQUIRED FOR ONE PART NUMBER.

ACCORDING TO THE FOLLOWING VARIANTS

FOR THE REQUIREMENT OF 1,200,000 COMPONENTS PER YEAR, 9 MACHINES WITH 2 SPINDLES ARE REQUIRED FOR ONE PART NUMBER.

ACCORDING TO THE FOLLOWING VARIANTS

IMPROVEMENT

86.81%

-8 HOUR SHIFTS = 155 PIECES

-6 DAYS A WEEK = 2,790 PIECES

-48 WORKING WEEKS = 133,920 PIECES

-8 HOUR SHIFTS = 166 PIECES

-6 DAYS A WEEK = 3,000 PIECES

-48 WORKING WEEKS = 144,000 PIECES

FOR THIS AMOUNT TRANSMECANICA EVEREST REQUIRED 9 MACHINES WITH 2 SPINDLES TO REACH THE VOLUME EXPOSED.

FOR THIS AMOUNT TRANSMECANICA EVEREST REQUIRED 9 MACHINES WITH 4 SPINDLES TO REACH THE VOLUME EXPOSED.

ESTIMATED

INVESTMENT

ESTIMATE INVESTMENT

TOTAL INVESTMENT

$50M USD

GOAL

2024

100%

658,168

MACHINERY PRODUCTION LINE TIME & PIECES DELIVERIES RAMP-UP

SEPTEMBER

2024

90%

¡PIECES !

AUGUST

2024

68.5%

1 MACHINES WITH 4 SPINDLES AND 1 WITH 2 SPINDLES = 144,000 FINISHED PIECES

46%

JULY

2024

2 MACHINES WITH 4 SPINDLES AND 2 WITH 2 SPINDLES = 288,000 FINISHED PIECES

JUNE

2024

22.5%

MAY

2024

2 MACHINES WITH 4 SPINDLES AND 2 MACHINES WITH 2 SPINDLES = 288,000 FINISHED PIECES

2 MACHINES WITH 4 SPINDLES AND 2 WITH 2 SPINDLES = 288,000 FINISHED PIECES

2 MACHINES WITH 4 SPINDLES AND 2 MACHINES WITH 2 SPINDLES = 288,000 FINISHED PIECES

TOTAL 1,200,000 PIECES

NOTE: INFORMATIONAL PURPOSES ONLY