Premier Designs Inc.

Cost Estimating & Project Management

Excavation/Foundation

Excavation/Foundation

- Property Line

- Cleared Area

- Excavated Area

Site Work

&

Excavation

Leavens Construction

Total Cost: $14,500

2 Days

1 Days

2 Days

Site Clearing

Basement Excavation

Grading

Foundation

&

Flat Work

Estimated Total Cost: $54,500

Estimated Labour Cost: $25,000

Estimated Material Cost: $29,500

2 Days

5 Days

Footings

Foundation Walls

Flatwork

Total Concrete: 101 cubic meters

Floor Framing & Steel

Framing

Wall Framing

Materials: $48,000

Labour & Equipment: $ 35,000

Total: $83,000

Steel: 2 days

Floor: 4 days

Walls: 8 days

Roof: 6 days

Framing

Roof Framing

Exterior Finishes

Fibre Cement Siding with

Aluminum Finishes

LaFitt Stone Wainscotting

Exterior

Finishes

Siding

Rob's Siding Inc.

Total Cost: $22,000 + hst

Labour Cost:

$10,000 + hst

Material Cost:

Fiber Cement Siding - $7500 + hst

Aluminum - $4500 + hst

Downspouts

Soffit & Facsia

Eavestrough

Fiber Cement Siding

Franke Masonry

Masonry

Material Cost:

LaFitt (small) Stone - 530sf = $3000 + hst

LaFitt (large) Stone - 220sf = $1250 + hst

2" Limestone Sills - 32 pcs = $2900 + hst

Additional Material = $1050 + hst

Material Total = $8200 + hst

Labour Cost:

705sf = 12,000 + hst

Total Cost: $20,200 + hst

Interior Finishes

Hardwood & Luxury Vinyl Plank Flooring

Fireplace & Masonry Panel System

Interior

Finishes

Flooring

A-1 Flooring Canada

Total Cost: $26,350 + hst

Hardwood - American Black Walnut (6" x 3/4")

Material Cost: (including waste)

1600 sf = $12,600 + hst

Labour Cost :

Nail with Glue Assist = $4750 + hst

LVP - Evoke Vital Drew Walnut (5 7/8" x 48" x 1/4")

Material Cost: (including waste)

1150 sf = $6750 + hst

Labour Cost :

Tongue & Groove = $2250 + hst

Franke Masonry

Fireplace Wall

Fireplace Masonry Wall

Charcoal Black Shadow Panel System:

130 sf = $2270 + hst

Stone Hearth 16' x 6' = $250 + hst

Bags of Ardex 77 - 4 bags = $330 + hst

Cement Board - 4 pcs = $250 + hst

Total Material Cost = $3100 + hst

Labour Cost = $2400 + hst

Total Cost: $5500 + hst

M-E-P

Mechanical Quote

Electrical Quote

Plumbing Quote

Mechanical

Electrical

Plumbing

(MEP)

Mechanical

Bob Reid Heating & Cooling

Equipment + Labour Cost:

Furnace & Air-Conditioner = $11,000 + hst

Heating Recovery Ventilator (HRV) = $2500 + hst

Tankless Hot Water = $4000 + hst

Exhaust Fans (4) = $2500 + hst

Duct Work = $14,000 + hst

Gas Line = $2000 + hst

Total = $36,000 + hst

Phase 1

Phase 2

Armstrong Air - 1.5 Ton

Armstrong Air - 45,000 BTU

Verhoef Electric Inc.

Materials & Labour Quote:

Total = $29,750 + hst

Optional Items:

Ev Rough-In = $450 + hst

LED Under Cabinet Lighting = $195/per + hst

Electrical

Go Green Plumbing Ltd.

Plumbing

Material & Labour Cost:

Rough-in = $15,500 + hst

Accessibility Fixtures Cost:

KOHLER Santa Rosa Comfort Height Toilets

$539.00/each x 2 = $1100 + hst

Wall Mounted Vanity (31")

$1350/each x 2 = $2700 + hst

Total Fixture Cost = $3800 + hst

Project Summary

Summary

Cost

Rosehill Ranch Costs

Site Work: $14,500

Concrete: $54,500

Framing: $83,000

Exterior Finishes: $42,200

Electrical: $29,750

Plumbing: $19,300

HVAC: $36,000

Interior Finishes: $31,850

Total Costs Counted: $311,100 + hst

Property: $350,000

Budget: $1,200,000

Available: $538,900

Schedule

Rosehill Ranch Schedule

Site Work: 5 days

Concrete: 30 days

Framing: 27 days

Exterior Finishes: 27 days

Electrical: 13 days

Plumbing: 13 days

HVAC: 8 days

Interior Finishes: 57 days

Total Duration: 112 days (5 months)