- Property Line
- Cleared Area
- Excavated Area
Total Cost: $14,500
2 Days
1 Days
2 Days
Estimated Total Cost: $54,500
Estimated Labour Cost: $25,000
Estimated Material Cost: $29,500
2 Days
5 Days
Floor Framing & Steel
Wall Framing
Materials: $48,000
Labour & Equipment: $ 35,000
Total: $83,000
Steel: 2 days
Floor: 4 days
Walls: 8 days
Roof: 6 days
Roof Framing
Fibre Cement Siding with
Aluminum Finishes
LaFitt Stone Wainscotting
Total Cost: $22,000 + hst
Labour Cost:
$10,000 + hst
Material Cost:
Fiber Cement Siding - $7500 + hst
Aluminum - $4500 + hst
Material Cost:
LaFitt (small) Stone - 530sf = $3000 + hst
LaFitt (large) Stone - 220sf = $1250 + hst
2" Limestone Sills - 32 pcs = $2900 + hst
Additional Material = $1050 + hst
Material Total = $8200 + hst
Labour Cost:
705sf = 12,000 + hst
Total Cost: $20,200 + hst
Hardwood & Luxury Vinyl Plank Flooring
Fireplace & Masonry Panel System
Total Cost: $26,350 + hst
Hardwood - American Black Walnut (6" x 3/4")
Material Cost: (including waste)
1600 sf = $12,600 + hst
Labour Cost :
Nail with Glue Assist = $4750 + hst
LVP - Evoke Vital Drew Walnut (5 7/8" x 48" x 1/4")
Material Cost: (including waste)
1150 sf = $6750 + hst
Labour Cost :
Tongue & Groove = $2250 + hst
Fireplace Masonry Wall
Charcoal Black Shadow Panel System:
130 sf = $2270 + hst
Stone Hearth 16' x 6' = $250 + hst
Bags of Ardex 77 - 4 bags = $330 + hst
Cement Board - 4 pcs = $250 + hst
Total Material Cost = $3100 + hst
Labour Cost = $2400 + hst
Total Cost: $5500 + hst
Mechanical Quote
Electrical Quote
Plumbing Quote
Equipment + Labour Cost:
Furnace & Air-Conditioner = $11,000 + hst
Heating Recovery Ventilator (HRV) = $2500 + hst
Tankless Hot Water = $4000 + hst
Exhaust Fans (4) = $2500 + hst
Duct Work = $14,000 + hst
Gas Line = $2000 + hst
Total = $36,000 + hst
Phase 1
Phase 2
Materials & Labour Quote:
Total = $29,750 + hst
Optional Items:
Ev Rough-In = $450 + hst
LED Under Cabinet Lighting = $195/per + hst
Material & Labour Cost:
Rough-in = $15,500 + hst
Accessibility Fixtures Cost:
KOHLER Santa Rosa Comfort Height Toilets
$539.00/each x 2 = $1100 + hst
Wall Mounted Vanity (31")
$1350/each x 2 = $2700 + hst
Total Fixture Cost = $3800 + hst
Site Work: $14,500
Concrete: $54,500
Framing: $83,000
Exterior Finishes: $42,200
Electrical: $29,750
Plumbing: $19,300
HVAC: $36,000
Interior Finishes: $31,850
Total Costs Counted: $311,100 + hst
Property: $350,000
Budget: $1,200,000
Available: $538,900
Site Work: 5 days
Concrete: 30 days
Framing: 27 days
Exterior Finishes: 27 days
Electrical: 13 days
Plumbing: 13 days
HVAC: 8 days
Interior Finishes: 57 days
Total Duration: 112 days (5 months)