Etihad Rail Stage-1

Ansaldo STS S.p.A

Project Intro

Scope of Work description

  • Activity (Design, engineering, supply, commissioning, installation, Warranty and DLP management )
  • Technologies (ERTMS) L2 SIGNALLING SYSTEM which encompasses one RBC and two WSPs Interlocking, TELECOM SYSTEM which encompasses a Multi Service Network (MSN) and a GSM-R system, TMS installed in a temporary Operational Control Centre, SCADA AND OTHER MINOR SYTEMS such as a FCS, ACS, FDS, FES, CCTV, BMIS, Voice Recording and Master Clock.
  • Numbers LINE LENGTH   264 km; STATIONS  0; DEPOT  1; TRAINS  (not part of SoW)

Executive Summary

Overall status (Progress/Key milestones achieved)

  • Section 1 has a physical progress of the 100%
  • Section 2 has a physical progress of the 100%
  • Defect Liablity Period completed on 8th June 2017
  • Submission of Final RAMS Demonstration Report
  • Completion of SCADA interface testing to Data Concentrator

Our Team

Our Team

Manuel Giros

Area Manager

Middle East

Castagna Raffaele

Maintenance North Europe and Middle East

Mohamamd Ali

Maintenance Manager

Afraz Iftikhar

Maintenance Engineer

Syed Hammad

Maintenance Engineer

Project Status

Engineering

Project Start

Warranty

Commissioning

April 2015

January 2012

December 2015

December 2020

Project Status

Procurement

Installation

DLP

October 2015

October 2014

June 2017

Outstanding Work

Outstanding Work

Balise Failures

Open Defects

3

1

  • We are receiving a big number of Balise Failures as a warranty claims from Client. A good stock of Balise is needed.
  • B0101-S01-GOP-RX-00134 GSM-R Covergae at SHA Facility
  • B0101-S01-GOP-RX-00276 TMS and VCP Workstation Frozen Issue
  • B0101-S01-GOP-RX-00474 D&M Workstations (IXL1; IXL2; RBC) - Intermittent Alarms
  • B0101-S01-GOP-RX-00615 VMS Laser Scanner

Wheel Mesauring System

2

  • We are experiencing delay from the supplier DMA for the testing and commissioning of WMS

Next Steps

  • Leonardo presence is required for the timely completion of important Defect No.134 related to the GSM-R Coverage.

  • Target completion date for the outstanding defects is 31st March 2018

  • Completion of WMS Testing and Commissioning is planned for 28th February 2018.

  • Good number of Balise to be sent from Italy.

Next Steps

Risk Analysis

Risk Analysis

Very Likely

Agreement with SDT for Change Order and Extenion of Time Claim

Likelihood

Unlikely

Minor

Major

Impact

Opportunities

Opportunities

Maintenance Contract With ERDB

1

2

Spare Parts to ERDB