Introducing 

Prezi AI.

Your new presentation assistant.

Refine, enhance, and tailor your content, source relevant images, and edit visuals quicker than ever before.

Loading…
Transcript

the

WHY

we need a

face lift

our

comps

amenities

our competitors

Liv North Scottsdale

hallways

Liv North Scottsdale

Our Competitors

our Liv customers

our

customers

the

PLAN

leasing +

hub

Liv leasing office

Liv hub

other

amenities

Game Room

Courtyard

Business Center

Cabana : Pool Area

hallways

hallways

Total requested for approval: $1,375,000

the

budget

residential hallways = $527K

hallways

  • Flooring = $251K
  • Paint = $110K
  • Artwork = $109K
  • Lighting = $75K
  • Accessories = $14K

Misc - Freight, tax, design fees = $157K

MISC

  • Freight and tax = $114K
  • Design fee = $35K
  • Low Volt/other = $6500

Hub/Cafe/Working Space = $96K

  • FF&E = $73K
  • Flooring = $24K
  • Added Amazon lockers = $15K

Hub/Cafe/Work Spaces

Courtyard A = $92K

Courtyard A

  • FF&E = 27K
  • Tile work = $10K
  • Misc demo/construction = $10K
  • Ramada = $8500
  • New turf = $8K
  • BBQ cabinet rebuilt = $7500
  • Landscape = $7500
  • Liv branded custom fence = $5600
  • New Grills = $5K
  • Market lights = $3K

Game Room = 77K

Game area

  • Game Room = $77K
  • FF&E = 50K
  • Demo/construction = $10K
  • Flooring = $7K
  • Appliances/lighting = $4K

Leasing area = $74K

Leasing area

  • FF&E = $26K
  • Demo/construction = $21K
  • Wall treatments = $8K
  • Flooring = $7K
  • Accessories = $5K
  • Acoustical install = $2500
  • Liv sign/electrical = $2500

next

steps

  • Hub/café = $96K
  • Resident Hallways = $527K
  • Front doors included?
  • Game Room = $77K
  • Leasing Area = $74K
  • Pool area = $36K
  • Courtyard A =$92K
  • Business Center = $22K
  • Exterior lighting = $100K
  • New turf: Bark park, rooftop deck, pool = $41K

prioritization

TIMELINE:

4/20/2020-9/15/2020

Order FF&E and engage Contractors = 4/20/20

Demo and renovation of common spaces = 5/1 – 6/30 (two months)

Building B Residential hallways = 5/1 – 5/31 (one month)

Building A hallways = 6/1 – 6/19 (three weeks)

Building C hallways = 6/22 – 7/3 (two weeks)

Building D hallways = 7/6 – 7/17 (two weeks)

All hallway lighting installed = 8/15 – 9/15 (one month)

FF&E installed = 9/1 – 9/15 (two weeks)

Project completion date: 9/15/20