PU-COLLEGE OF ENGINEERING

Dr. Raed Jarrah

Dr. Samer Al Zahab

FINAL YEAR PROJECT II

30.1.2020.

RAHA HEALTHCARE PROJECT

GROUP 6

Introduction

Demand Assessment

Introduction

South Lebanon Lacks:

  • Highly Qualified Hospitals
  • Advanced Medical Equipment
  • Highly Equipped Laboratories
  • Health Care Clinics

Scope of the Project

Scope of the Project

The scope of the project is to develop two stories reinforced concrete structural building.

The first story will be subdivided into three zones:

Zone A: Highly equipped with advanced medical equipment and laboratories.

Zone B: Administrative and Finance Departments

Zone C: Health Care Clinics

The second story is dedicated to serve patients by supplying them with suitable patient rooms and comfortable beds.

Analysis & Design

Software Programs

  • SAFE
  • ETABS
  • S-CONCRETE

Analysis & Design

MODELING + ANALYSIS

CHECK #2: Sway Displacement

CHECK #3: Story Drift

CHECK #1: Long Term Deflection

Allowable Deflection= L/250=650/250=26

Allowable S=(h(T)- h(R))/500= (8950-2500)/500= 12.9

Factored Drift= 0.7*R*Drift <0.02

FRAME SECTION DESIGN

Section #1: Columns Design

Section #2: Beams Design

Beam Section A

Beam Section B

Beam Section D

Beam Section C

Section #3: Slab Design

Solid Slab Punching Shear Check

Solid Slab Flexural Design

RAFT FOUNDATION ANALYSIS + DESIGN

CHECK#1: Raft Settlement Check

Max. Allowable Settlement Limit = 100mm (Cohesive Soil)

CHECK#2: Raft Uplift Check

Uplift Values Shall Be Less than Zero

CHECK#3: Punching Shear Check

Max. Punching Shear Ratio =0.7716 < 1

CHECK#4: Raft Reinforcement Check

Flexural Reinforcement

  • Top Layer: T16@14cm
  • Bottom Layer: T12@14cm

Additional reinforcement

  • Long Direction (L=2m): T16@14cm
  • Short Direction (L=1.5m): T12@14cm

Bill of Quantities

BOQ SUMMARY

Bill of

Quantities

02 SITE CONSTRUCTION

Bill of Quantities

01

SITE WORKS

CONCRETE WORK RATES IN LEBANON

02 CONCRETE WORKS

03 CONCRETE WORKS

05

REINFORCEMENT STEEL

Bill of Quantities

04 MOISTURE & THERMAL PROTECTION WORKS

CONSTRUCTION SCHEDULE

Construction Schedule

MILESTONES

  • START: 1 June 2020
  • FINISH: 16 October 2020

Total Duration: 100 Days

GANT CHART

GANT CHART was developed by PRIMAVERA Software

GANT CHART was developed by PRIMAVERA Software

Conclusion

THANK YOU