To Do Exercise
If Activities 1-2, 2-3, 2-4, 2-5, 3-4, 4-5 and 5-6 have a normal duration of 13, 16, 19, 17, 18, 15, 13 days, normal cost is Rs 600, Rs 4400, Rs 1600, Rs 1200, Rs 4000, Rs 6000 and Rs 800 and crash duration of 12, 14, 15, 15, 14, 13 and 12 days and Crash cost is Rs 1000, Rs 6200, Rs 3800, Rs 6000, Rs 8000, Rs 7700, Rs 600 respectively. Find the Cost slope of all the activities
A milestone anticipates what the project is supposed to achieve at a pre-set date.
It should describe a desired state of affairs, a desired future situation.
There are two important aspects to this.
Is a summary schedule that identifies the major schedule milestone in a chart
It’s a way of advising top management of the status of the project and should act as a spur to the project team to meet these guidelines
Milestone Slip Chart/trend charts
It compares the SCHEDULED amount of work with what has actually been PERFORMED, to determine if COST, SCHEDULE, and WORK (SCOPE) ACCOMPLISHED are progressing as planned