Work Completed

  • Processing rate
  • Landfill composition
  • Articulated truck cycle time
  • Equipment modifications

Processing Rate

Equipment Modifications

Excavation (Cell D)

Loader

7,578 cubic yd/day

*12 months

950K to 960K

Mining (Cell C)

1,124 cubic yd/day

Dozer

*12 months

D5K2 to D9

Mining (South Thumb)

1,186 cubic yd/day

*12 months

Landfill Composition

Articulated Truck Cycle Time

Minimum: 5 trucks

Maximum: 10 trucks

Project Schedule

Average: 8 trucks

Revised Scope & Gantt Chart

Work in Next 2 Weeks

Logistics Plan

  • Sequencing
  • Phases of mining & excavation
  • Stock piles
  • Soil, rocks, metals, wood, concrete
  • Area & height

Block Flow Diagram

  • Mass balance

Waste Characterization

TG-C Trash Grapples

Hydraulic Thumb

G130B Contractors Grapple

H115 S-Hammer

Attachments

Project Status Presentation 4

Project Overview

March 11, 2013

1) Literature Review

2)Landfill Mining &

Excavation Plan

3)Environmental Controls

4) Formation of Budget

5)Documentation

Cinder Lake Landfill: Re-sequencing Cell D

Prepared by: Aspen Engineering & Environmental Services

Saleh AlAzmi

Coral Martz

Shayla Woodhouse