Excavation (Cell D)
Loader
7,578 cubic yd/day
*12 months
950K to 960K
Mining (Cell C)
1,124 cubic yd/day
Dozer
*12 months
D5K2 to D9
Mining (South Thumb)
1,186 cubic yd/day
*12 months
Minimum: 5 trucks
Maximum: 10 trucks
Average: 8 trucks
Logistics Plan
Block Flow Diagram
Waste Characterization
TG-C Trash Grapples
Hydraulic Thumb
G130B Contractors Grapple
H115 S-Hammer
Attachments
1) Literature Review
2)Landfill Mining &
Excavation Plan
3)Environmental Controls
4) Formation of Budget
5)Documentation
Cinder Lake Landfill: Re-sequencing Cell D
Prepared by: Aspen Engineering & Environmental Services
Saleh AlAzmi
Coral Martz
Shayla Woodhouse