Vendor evaluation

(No mandatory and No recommended)

Progress

Dated 26/03/2016

How many equipment are checked ?

(Based on CNCEC proposal)

Qty

1)Delayed answer from CNCEC .

2)No QC/QA specialist inKPI.

3)Some general information without any particular location in proposed discount from CNCEC

Total equipment : 66,474

Mandatory equipment: 15

Recommended equipment: 208

KPI selected equipment : ~18,400

Slected equipment percentage: 27%

CNCEC discount suggestion: 49,989,649 US$

Mandatory and Recomended: ~19,000,000 US$

slected equipment after technical evaluation:

~9,149,403 US$

Percentage : ~19 % (based on total CNCEC offer)

* This is not final result and we will still working on it because of CNCEC incomplete answer

Reason of delay

Potential Amount:

Preliminary calculation

35,761,095 US$

New calcualtion after technical evaluation:

~30,000,000 US$

Procurement Evaluation (example)

Progress till 26/03/2016

Summery of calculation:

Technical Evaluation (example)