Loading presentation...
Prezi is an interactive zooming presentation

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Make your likes visible on Facebook?

Connect your Facebook account to Prezi and let your likes appear on your timeline.
You can change this under Settings & Account at any time.

No, thanks

DIRECT OWNER PURCHASE ORDER INSTRUCTIONS

No description
by

Rita Higgins

on 29 April 2016

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of DIRECT OWNER PURCHASE ORDER INSTRUCTIONS

Review and Approval
Upon review and approval of the DOPO package, the project manager is to forward the package to the F&S Business Office for accuracy. The Business Office will submit the paperwork to Purchasing to issue a purchase order.
Issue
A copy of the purchase order issued by UCF will be forwarded to the project manager, who will in return forward a copy to the contractor. The contractor will send a copy of the purchase order to their subcontractor and vendor.
Verify
Once the invoice has been verified, the contractor will sign the face of the invoice indicating approval for payment and forward the Invoice Summary Sheet to the the project manager for approval who then submits it to the Business Office.
Prepare
The contractor will prepare a deductive change order for all RPO's and submit the paperwork to the project manager.

*****

Note: The Facilities & Safety (F&S) Business Office will not be able to process the request packet without the matching deductive change order.


Review
The contractor is responsible for reviewing invoice for accuracy.
DIRECT OWNER PURCHASE ORDER BLUE PRINT
Check
The actual check will be mailed from the UCF Finance & Accounting Department to the vendor.


The vendor provides the invoice to subcontractor. The subcontractor completes the Invoice Summary Sheet and submits the invoice to the contractor.
Provide
NOTE
UCF cannot be responsible for construction delays due to non-compliance with these procedures.
View Comprehensive DOPO Instructions