St. Philip the Apostle Catholic Church

Additions and Renovations

Tim Laframboise

Project Director

CONSTRUCTION

PRECONSTRUCTION

Randy Kies

Preconstruction Manager

Taylor Pappalardo

Assistant Project Manager

Trevor Powell

Project & Construction Manager

Allen Burris

Superintendent

Trevor Powell

Project & Construction Manager

or

Randall Long

Superintendent

Taylor Pappalardo

Assistant Project Manager

Relevant Experiences

Relevant Experience

St. Luke Catholic Church

St. Luke Catholic Church

Our Lady of the Lourdes

Queen of the Apostles

Lifepointe Church

New Birth Church of Charlotte

Grace Covenant Church

Engagement

Pre-Construction

A. INITIAL PROJECT EVALUATION:

  • Site qualification
  • Consultation during project development
  • Conceptual Performance budgeting
  • Projected project schedule

B. SCHEMATIC DESIGN:

  • Utilize technical Site Evaluation and Analysis process
  • Site design input
  • Floor plan and exterior design input
  • Building systems conceptual design input
  • Statement of probable cost and schedule
  • Evaluation of alternatives

C. DESIGN DEVELOPMENT:

  • Inject past experiences into the design process
  • Further development of schematic design concepts
  • Evaluate design / build scope of work possibilities
  • Implement Value Engineering into initial design stage
  • Site lighting design
  • Design reviewed with Architect of Record and Specified Project

D. CONSTRUCTION DOCUMENTS:

  • Detailed plan and specification review
  • Implement subcontract qualification process
  • Conduct intensive subcontractor bid procedure
  • Conduct open book review of all bids with the Specified Project and Architect of Record for Selection

Site / Logistics Plan

Keeping the Church Operational

Option 1 - Relocate Worship

  • Relocate office staff/space to the Social Hall.
  • Install temporary drywall partition in the Lobby to close of the space to be demolished.
  • Start demolition of the Education Center Building and Addition.
  • Procure materials for the Vestibule and Office Addition.
  • Temporarily relocate the Worship Space to the Social Hall while demolition, underground, concrete, and steel construction occurs for the Lobby addition.
  • Continue to use Social Hall for worship if desired.
  • Install temporary access walkways into the Existing Lobby. If desired, temporary tunnels could be constructed through the Construction Site. Coordination and review with Little will be needed to determine egress numbers/doors required.

Operations

Option 2 - Use Existing Worship Space, Walking Distance Concern

  • Follow same progression as Option 1, but install temporary doors in temporary wall along with sidewalk between new Education Building and existing Social Hall.
  • Access walkway from Lower Parking Lot and/or through the Social Hall.

Estimate

Division 1 - General Requirements

Division 2 - Sitework

Division 3 - Concrete

Division 4 - Masonry

Division 5 - Metals

Division 6 - Wood and Plastics

Division 7 - Thermal and Moisture Protection

Division 8 - Doors and Windows

Division 9 - Finishes

Division 10 - Specialties

Division 15 - Mechanical

Division 15 - Plumbing

Division 16 - Electrical

Division 19 - Misc. Project Costs

General Liability

Subcontract Bonds

Builder's Risk - Owner

Performance and Payment Bond

Building Permit

Design/Budget Contingency

Contractor Contingency

Fee

Total:

$ 316,142

$ 331,171

$ 126,949

$ 166,941

$ 26,982

$ 278,820

$ 144,463

$ 158,085

$ 268,392

$ 33,822

$ 180,030

$ 112,832

$ 255,051

$ 52,697

$ 8,620

$ 29,342

$ 0

$ 34,480

$ 14,500

$ 100,568

$ 100,568

$ 132,912

$ 2,873,366