Supervised by:
Dr. Fawaz Al-Zgoul
MHC – PMS is a web-based system that focuses on establishing a repository for all the mental patients, it makes a repository that stores all the patient’s information and generates reports and warnings to follow up with patients.
The system has different workflows since it has different components and accounts
This project aims to develop a reliable management system that helps in following up mental patients and to improve and increase the focus on mental illness health care systems. This system is a web based system that must be implemented by front-end and back-end development with database connection.
MHC – PMS is responsible for all of the following up and previewing mental health problems in a systematic and organized way.
The stakeholders of this system are doctors, nurses, patients, receptionists and administrator.
The minimum software and hardware requirements of the user to be able to access PHC-PMS.
To be able to log in and use this system, all the users must have internet connection, any available internet browser and any computer device or smart devices like phones and tablets with the ability to access the internet.
The best process model for this system is the
Waterfall system model
, which is the system model for the plan-driven process.
Task software allows groups of users to work together more cohesively to quickly and thoroughly complete projects.
The MHC-PMS system is expected to take 14 months and from project approval to launch the MHC-PMS program.
The following is a high-level schedule of significant stations for this initiative:
Feb 2, 2020: Initiate Project
February 10, 2020: determine the requirement (functional , non-functional)
March 10 , 2020: started project design .
April 1, 2020: Implementation ( prototype).
Dec 1, 2020 :complete Implementation code .
Feb 1, 2020: System Testing .
April , 1,2021: Complete the project and Launch the site.
A Gantt chart is a visual view of tasks scheduled over time is shown below:
The parts that a healthcare adviser could help you in deriving the accurate data with the effective feasible study
In order to succeed, we as a development team had to implement monitoring and evaluation phases, these phases cover all the techniques used to track and monitor the system. The main monitoring methods used are:
Target Users
Functional Partitioning
Functional Requirement Definition
Functional Requirement.
Non-functional Requirement
1- A patient can view his/her information , make appointments , cancel appointments .
2- Doctors can update on patient records , view patient records , create new patient records , cancel and delete records .
3- Administrative Manage appointment , cancel appointment , control the system based on the authority of the system.
4- Clinical staff : view and create records ,Fill the patient's record with his information.
Use case diagram
Context Diagram
For modeling MHC-PMS systems, we will focus on the
interaction, behavioral, and structural perspectives.
Activity Diagram
State Chart Diagram
Test Cases for sign up - Log in operations