Introducing 

Prezi AI.

Your new presentation assistant.

Refine, enhance, and tailor your content, source relevant images, and edit visuals quicker than ever before.

Loading…
Transcript

Project time management

Challenges of project time management in public sector

Managing project time - challenges

- Private-sector projects often have time constraints

- Private-sector projects need to comply with external deadlines for compliance with laws or government regulations.

- Public-sector agencies and managers have very low tolerance for schedule risks and project delays

- Budget and spending time limits

- The requirements of higher-level agencies

Most important issues associated with defining project activities

We will assign attributes to those activities, which can include the number,

description, predecessors and successors, resource requirements, constraints, and other factors.

Putting the Activities in a Logical Order

Activities, methods and tools associated with creating the project schedule

In order to determine the right sequence of activities, we have to ask

ourselves a simple question for each one: What activities have to be done

before this one? That is called identifying dependencies. It tells us which

activities are dependent on other activities.

Some dependencies are mandatory. That means that we have to do

some activities in a required order. Other activity relationships are discretionary. That means that we

prefer to do them in a certain order. Without thinking about it, those

preferences for doing things in a certain order are usually related to

reducing a risk that we are not comfortable with.

There are two methods for mapping project sequences and creating a

project network diagram:

  • the activity-on-node model (AON) --> places activities on the nodes of the diagram;
  • the activity-on-arrow method (AOA) --> puts the activities on the arrows.

two methods

Most organizations prefer the AON model, which is also referred

to as the precedence diagramming method (PDM).

With the constructed network diagram, we can literally see the link

between activities and are very close to being able to build our schedule.

On this diagram, duration estimates have been also added.

exemplary AON Project Network Diagram

Activity duration estimating identifies the time necessary for completion of the activities identified. We are not concerned with how long an

activity should take without the other demands on the time of our

resources; we want to estimate how long it will take them after considering their other assignments and duties. After we estimate durations and match those durations to the project

network diagram, we can determine the total length of the project. That

project duration can be compared to the project’s time constraints to see if

we have a realistic plan.

Estimating the duration of activities

Analogous estimating

This is the least accurate estimating method as it requires very little project data. In that method, we simply find another project or activity and identify

the length of it. We can then make simple adjustments based on the

differences between that project and the current project and derive an

estimate. Analogous estimating is often used to provide early, rough-order-of-magnitude estimates to establish budgeting parameters.

Parametric estimates

Parametric estimates are regarded as

more accurate than analogous estimates because they require more data so we can identify mathematical

relationships to help estimate durations. For example, if we were to attempt to determine how long it will take us

to write a software program estimated to require 100,000 lines of code,

we could find out what the standard is for the number of lines of code

that can be written in an hour and divide the total lines necessary by

the standard to determine the number of hours the project will take.

Three-point estimating

Three-point estimating

Relies on gathering information or expert judgment so it can minimize the impact of very high or very low estimates. It identifies the most optimistic estimate, the most

pessimistic one, and a midrange one. Those three estimates are added

with the midrange estimate being multiplied by a factor of four. The sum

is then divided by six, which pulls the high and low estimates toward

the midrange estimate.

Bottom-up estimating is considered the most accurate as it relies on the most project data. This method assigns durations

to individual activities. Those individual activity estimates, although they

employ the most project information, can be inaccurate, however, if the

same bias is applied to each activity estimate.

Bottom-up estimating

Resource Estimates

Identifying

the necessary resources

- resources that are necessary for completing each activity. It may seem that

identifying resources is more appropriate to project budgeting and cost

management. In fact, in identifying the necessary resources, we are not

concerned with the cost of those resources. We are only concerned with

identifying what resources are necessary for the performance of the

activities of the project.

Tools

- the use of buffers in the schedule - Schedule buffers are additional blocks of time placed in the project network diagram before activities or sequences of activities that are resource constrained

- Constrained resources - are one of the reasons for the project adage that ‘‘bad news moves forward but good news doesn’t.’’

Tools

OUTCOMES

The principal outcomes of activity resource estimating are the resource requirements for each activity and, perhaps, a resource breakdown structure (RBS), which is a hierarchical summary of resources necessary for the project.

Outcomes

Resource Breakdown Structure

best practices for activity resource estimating would include:

best practices for activity resource estimating

- Being realistic about the time required for accessing resources from outside the organization

- Being realistic about the availability of resources at the times necessary, especially if those resources are also working on other projects

- Being aware that changing priorities may make previously scheduled resources unavailable

- Documenting assumptions about resource availability in the project scope statement and charter and making those assumptions known in project status reports

Before creating the schedule

Creating the schedule (critical path method

  • put the activities that are necessary for creating the project's deliverables into a logical sequence
  • assign durations to the activities
  • identify needed resources
  • examine the schedule to identify the days that you intend to work
  • identify days off
  • check if there are any days, like events, that may affect the project

Create the project schedule

The critical path method is the most common one. It helps to identify the length of a project. This method analysis the path through the project network diagram that is composed of activities with the longest total of summoned durations. That longest path is the critical path, so named because every activity on the path, if delayed, delays the entire project.

The critical path method

Project network diagram

Analyze hardware needs (5 days)

-

Identify hardware options (2 days)

Start

-

Create recommendations for purchasing (3 days)

|

Identify possible vendors (2 days)

-

Example

Select vendors (7 days)

Contact purchasing (1 day)

|

Order hardware (1 day)

|

Identify hardware options (2 days)

|

Inspect hardware on delivery (3 days)

End

-

One of the biggest challenges in completing projects is balancing several projects at once. Most people have multiple projects in progress simultaneously. It is time-consuming and also, it takes a lot of effort. However, with a little planning, you can do much better than expected.

Conclusion

Four strategies

1. Change the time. If we have done good project planning and have concluded that we cannot get the project done on time, we can go back to the person who set the time and ask them to change it.

Compressing the project duration

2. Reduce the scope of our project. We can look at those activities on the critical path and examine the deliverable they are linked to. Maybe we can remove some of those from the project.

3. Throw some more resources at key

activities to reduce their duration (called crashing the schedule).

4. Fast-track the schedule. We need to evaluate the project network diagram and identify activities that are currently scheduled to be performed in sequence but that could be performed at the same time.

Best practices for time management in public-sector projects include the

following:

Best practices in public-sector time management

Build a plan for managing project time

Activity durations should measure the time that will be required.

Build in adequate time for processes that involve other departments

Evaluate options for duration compression

Make sure that job rules allow a team to perform the duties assigned

The schedule should be prepared with the best information

available and will always change

Learn more about creating dynamic, engaging presentations with Prezi