That's Scheduling
Impacts
For an impact to be considered,
- it must have an effect on the critical path;
- it usually cannot be caused by normal weather;
Schedule Impacts
- Generally an Schedule Impact Analysis is required
- SIA's show the impact of an event(s) to the critical path
- A fragnet is created to show the impacting activity
Changes
Contractor Submittals
- Is it reasonable, achievable, and logical?
- Are there changes and what are the impacts?
Contractor Progress
Southgate CTDR
CPM Schedule Basics
SiteManager
CTDR Flow Chart
Schedule Example
Why is it important?
What is it?
Why is it important?
What do I need to know?
- A means to track progress
- Protects both Owner and Contractor
- Tool to plan the work and work the plan
CPM - What is it?
- Activities tied together in a logical sequence
- Production Rates
- Weather Data
- Plans
- Specifications
- Restrictions/Limitations