Introducing 

Prezi AI.

Your new presentation assistant.

Refine, enhance, and tailor your content, source relevant images, and edit visuals quicker than ever before.

Loading…
Transcript

MOSE

TIDE BARRIER

MOSE (Modulo Sperimentale Elettromeccanico)

INTRODUCTION

MOSE is a project intended to protect the city of Venice, Italy, and the Venetian Lagoon from flooding.

POINT 1

1. The project is an integrated system consisting of rows of mobile gates installed at the Lido, Malamocco, and Chioggia inlets

POINT 2

2. Together with other measures, such as coastal reinforcement, the raising of quaysides, and the paving and improvement of the lagoon, MOSE is designed to protect Venice and the lagoon from tides of up to 3 metres

POINT 3

3. Currently it is raised for tides of more than 110 centimetres.

MAIN OBJECTIVE

OBJECTIVES

The aim of MOSE is to protect the lagoon, its towns, villages, and inhabitants along with its iconic historic, artistic, and environmental heritage from floods, including extreme events.

POINT 1

MOSE, together with reinforcement of the barrier island, has been designed to provide protection from tides of up to 3 metres (9.8 ft) in height.

POINT 2

MOSE is flexible and can be operated in different ways according to the characteristics and height of the tide.

POINT 3

The gates are independent and can be operated separately, all three inlets can be closed in the case of an exceptional event or each inlet can be partially closed.

OPERATING PRINCIPLES

OPERATING

PRINCIPLES

MOSE consists of rows of mobile gates at the three inlets, which temporarily separate the lagoon from the sea in the event of a high tide. There will be 78 gates divided into four barriers.

Under normal tidal conditions, the gates are full of water and rest in their housing structures

STEP 1

STEP 2

When a high tide is forecast, compressed air is introduced into the gates to empty them of water, causing them to rotate around the axis of the hinges

The gates rise up until they emerge above the water to stop the tide from entering the lagoon. When the tide drops, the gates are filled with water again and return to their housing.

STEP 3

POINT

To guarantee navigation and avoid interruption of activities in the Port of Venice, when the mobile barriers are in operation, a main lock is under construction at the Malamocco inlet to allow the transit of large ships, while at the Lido and Chioggia inlets there will be smaller locks to allow emergency vessels, fishing boats and pleasure craft to shelter and transit.

CONSTRUCTION

There are three inlets

1. Lido

2. Malamocco

3. Chioggia

CONSTRUCTION

The gates consist of metal box-type structures 20 metres (66 ft) wide for all rows, with a length varying between 18.5 and 29 metres (61 and 95 ft) and from 3.6 to 5 metres (12 to 16 ft) thick, connected to the concrete housing structures with hinges, the technological heart of the system, which constrain the gates to the housing structures and allow them to move.

LIDO INLET

1. There will be two rows of gates at the Lido inlet (21 mobile gates for the North barrier Lido-Treporti and 20 mobile gates for the South barrier Lido-San Nicolò).

LIDO INLET

2. Lido inlet consist of a lock, which allow small craft and emergency vessels to shelter and transit when the gates are raised.

3. At the centre of the inlet, a new island has been constructed to act as an intermediate structure between the two rows of mobile gates. This island will accommodate the buildings and plant for operating the gates

MALAMOCCO INLET

1. There is one row of 19 gates at the Malamocco inlet

2. In April 2014, the lock for the transit of large ships becomes operative to avoid interference with port activities when the gates are in operation.

MALAMOCCO INLET

3. Outside the inlet, a 1,300-metre (4,300 ft) long curved breakwater designed to attenuate tidal currents and define a basin of calm water to protect the lock has been completed.

CHIOGGIA INLET

1. There is one row of 18 gates at the Chioggia inlet.

2. Work has been completed to construct a small craft harbour with double lock to guarantee transit of a large number of fishing vessels when the gates are in operation.

CHIOGGIA INLET

3. Outside the inlet, a 500 metres (1,600 ft) long curved breakwater has been completed.

SPECIFICATIONS

SPECIFICATIONS

1.The project utilises 1.6 kilometres (0.99 mi) of mobile barriers

2. MOSE has a total of 78 gates

3. The smallest gate is 18.5 by 20 by 3.6 metres

4. The largest gate is 29.5 by 20 by 4.5 metres

5. Three small locks allow the transit of fishing boats and other smaller vessels when the gates are in operation

6. There are 156 hinges

7. 30 minutes are required to raise the gates

8. 15 minutes are required to lower the gates back into their housing structures

9. During a tidal event, the inlet will remain closed for 4/5 hours, including barrier raising and lowering times

Learn more about creating dynamic, engaging presentations with Prezi