Holes can also made from another machine which is hole punching machine
After epoxy procedure, the wrapping papers at the conductor area are removed
Cutting
Dimension of cutting is standardize as shown below
- R and N - extra 14mm
- Y and B - extra 2mm
- Earthing - extra 22mm
If it the dimension is 200mm lesser than standard dimension, it means it requires joint for connections
Washing and Cleaning
Welding and Grinding
- Welding procedure is done when there are connections of metals at different angles are needed
Metal adjusting procedure before welding
Welding process
- Metal has oily and dusty surface
- it is cleaned with soap and then proceed with clean water rinsing, at last, drying.
- it needs to be cleaned in order to have better results in epoxy procedure
Welded metals before grinding process
Removal of protruded materials
Grinding process to smoothen the welded material
Stock Storage Area
Stock Arrival and Storing
After Stamping
During Stamping
Shearing Machine (Copper)
Stamping
Drilling Process in making holes
Before Stamping
Hole Punching Machine
Cutting, Drilling and Bending
JIH- I 8CD (copper and aluminium)
- stocks that are newly arrived are stored in store room (tiny units), and outside store room (large unit, e.g: metals)
- every stocks acquiring requires record for reference
- the stamping procedure is similar for both aluminium and copper
- the stamping is required to make sure each flange end gap between each others are 12mm.
- Thus, R and N metal stamped with 18mm whereas Y and B metal stamped with 6mm
- Earthing metal stamped with 26mm
- Flange end dimension shall be approximately 68.5mm for R,Y,B,N
- Earthing end dimension is 69mm
Bending Machine
JIH- I 8A (aluminium)
1) 3 types of cutting machine
- Shearing Machine (Copper)
- JIH- I 8CD (Copper/ Aluminium)
- JIH- I 8A (Aluminium)
2) Drilling Machine
- mainly used for hole drilling or removal of unwanted parts
3) Bending Machine
Conductor Area Wrapping using Gloves
Conductor Area Wrapping
- Before proceed with epoxy procedure, conductor area is wrapped
- It prevents the epoxy affects the conductor area
- the cellophane tape and glove are used as the material for wrapping
Production Process
Labelling
Protection against jets of water, limited ingress permitted.
LINKK BUSWAY SYSTEMS (M) SDN BHD
3P4W+50%E
3 phase 4 way 50% earth
Epoxy and Testing
LV 1 KV AND BELOW
low voltage 1kV and below
1) Stocks Arrival and Storing
2) Cutting, Drilling and Bending
3) Welding and Grinding
4) Stamping
5) Washing and Cleaning
6) Conductor Area Wrapping
7) Epoxy and Testing
8) Colouring
9) Assemble and Testing
10) TOU Box
11) Packaging
12) Labelling
LK-129-1-01-R4-01
Removal of glue and dirt using pocket knife
BoQ Number for reference
- After the removal of wrapping papers and tape, workers are required to remove the melted glue around the conductor area
- Glue has bad effect for the colouring of flange end thus it must be cleared
- Metals are then tested to check any holes at the epoxy area to avoid leakage of current
Meter reading shown for the holes detection test after epoxy procedure
E
Conductive Brush used for scanning of holes during the test
N
Y
R
B
Epoxy and Testing
Presenter: Tang Kee Cheong
In epoxy process, the procedure is shown below:
- metals put into the first oven (210 degree celcius - 1 hour)
- metals taken out to be dipped into epoxy pool
- metals put into second oven, approximately 200 degree celcius for 1 hour 15 minutes when Papillon powder is used, 230 degree celcius for 50 minutes when platinum phase powder is used)
Thank You
226 degree Celcius on the second oven during the epoxy procedure
207 degree Celcius on the first oven during epoxy procedure
Packaging
Colouring
TOU BOX
- After all the necessary tests done, the completed model will be packaged with woods and stored
- The packaged stock are ready to be shipped
- No colouring machine in factory
- Metals sent to other factory for colouring
Assemble and Testing
Riveting procedure in housing formation
- There are many materials contained in the TOU Box
- However the materials are mainly from outsource
- The materials are assembled by workers to form a fully functional TOU Box
Applying polyester on the housing as insulator
Insertion of R,Y,B,N and E to the housing
- In assembly area, workers start to unwrap the materials obtained from the coloured metals as well as getting materials needed from the store for assemble process
Process of assemble are listed below:
1) Formation of housing of busduct
2) Insertion of RYBN and E to the housing
3) Addition of joint connection for shorter busduct
4) 5kV Testing on assembled busduct
Matching the dimension of conductor area
Riveting the top cover of the flange end elbow feeder
Connections of cable for 5kV test
Joint of feeders
Parameters used for the testing procedure