JAMES PAGET UNIVERSITY HOSPITAL
ALEX HOLMES
THANKS FOR LISTENING
NEIGHBORHOOD DAY
Monday 22nd-26th September
- Decking
- Planting
- Painting Wall
- New steps for rehabilitation
- Car for rehabilitation
- Paving
WEEKLY SUMMARY
WEEK 17
- Intumescent paint to first floor steel truss areas
- Installing temporary drainage systems
- Removal of existing roof planks
WEEK 18
- Concrete beams on FF being removed.
WEEK 19
- Carpenters start on new timber walkway on FF
- South elevation beginning to be removed
WEEK 14
- Installing mesh and pouring concrete to new 2nd floor
- Continuation of cold rolled steel for cladding being fixed
WEEK 15
- Fitting roof purlins to main roof ready for sheeting
- Demolish walls on 1st floor
WEEK 16
- Erecting new steel frame to substation area
- External cladding works to new roof
- Cleaning effluents off new 2nd floor slab ready for application of resin paint
SITE LAYOUT PLAN
WEEKLY SUMMARY
WEEK 11
- Walls being removed on first floor
- Water proofing to existing roof (Water issues begin)
WEEK 12
- Installation of new 2nd floor decking sheets
- Demolition of FF external walls above electrical substation
WEEK 13
- Start on external cladding works
WEEK 4
- Installing new mechanical supplies to GF Path Lab to enable us to disconnect services at FF
- Making up reinforcement cages for pile caps
WEEK 5
- Installing new piles including cutting piles down
- Start installing reinforcement cages to piles along with concrete
WEEK 6
- Plant room dismantled and removed from existing roof
CLIENT'S KEY OBJECTIVE
WEEK 1
- Site set up (Cabins, Foot paths, Fencing etc...)
- M&E Isolation works to first floor
- Form tower crane base
WEEK 2
- Concrete to crane base
- Setting out and surveys
- Excavating new hospital staff footpath
WEEK 3
- Site set up complete
- Erection of Tower Crane by 500t mobile crane
- Demolition on first floor begins
- Erect crash deck over electrical substation
- Cutting out roads & concrete areas for Pile Caps
WEEK 7
- Screw piling completed
- Commencement of steel frame
WEEK 8
- Continuation of steel frame
- M&E isolation works to FF area
WEEK 9
- Continuation of steel frame
- M&E isolation works to FF area
- WEEK 10
- Night shifts start (fire stopping due to M&E isolation works)
- Fix cold rolled steel to steel frame ready for cladding
- Putting patients first, we will. Treat patients, staff and the public with respect, Work considerately to ensure the patient experience is not unduly affected and Carry out a community/charity event.
- Aiming to get it right, we will. Complete all works safely with minimal disruption, Deliver the Project within the agreed schedule and Ensure any financial impacts to the Project are communicated promptly and effectively
- Recognising that everybody counts, we will. Communicate effectively with the Trust and its neighbours, Provide a weekly forum for staff representatives to review the work plan and agree contingency arrangements and Respond to all complaints promptly and effectively.
- Doing everything openly and honestly, we will. Promote the investment into Healthcare Services at the James Paget University Hospital and Be open and honest in all our dealings.
PROJECT DETAILS
- Project Value: £8.2m
- Contract Type: Major Works
- Contract Build Type: Traditional
- Contract: JCT 2011
- Phase 1: 28/04/14 - 19/01/15 (38 weeks)
- Day Case Theatres inc roof top plant room & structure
- Phase 2: 23/03/15 - 16/07/15 (17 weeks)
- Main threatre room/top plant room/structure/minor refurbishment
- Phase 3: 30/07/15 - 13/10/15 (11 weeks)
- Main Theatres Recovery, Theatre 5 & staff change area
- LADS: Section 1: £16k p/w, Section 2: £5k p/w, Section 3: £2k p/w
- Total Contract Period: 76Weeks
- Site Team: Tom, Tim, Barry, Scott, Tom J, Jeremy, Michael and I
- Main Hazard: Working above and around live hopsital including theatres, minor asbestos removal
- Weekend and Night works