PROBLEM STATEMENT
Structural Engineering Institute (SEI)
Competition Team
- Compete in the SEI student competition
- Develop the structural design for an addition to the engineering building
CONSTRAINTS
- Addition must be 20% larger than the existing building
- Existing is 93,000 square feet
- Addition will be 111,600 square feet
- Total: 204,600 square feet
- Design must be innovative
Stakeholders
- Department chairs
- Civil, Mechanical, Environmental, Electrical, Construction Management, Computer Science
By: Jonathan Gober, Jacob Hood, Sam Taylor
- Technical Adviser: Robin Tuchscherer
POTENTIAL PROBLEMS
- Tying the addition in to the existing building
- New building will require a larger footprint
PROJECT LOCATION
SCOPE OF SERVICES
GANTT CHART/SCHEDULE
BACKGROUND RESEARCH
Task 3: Design Foundation
- Task 6: Project Management
- Software
- Risa 3D, Revit, Sketch Up
Figure 2: Map of Project Site
- Standards/Codes
- IBC 2009, ASCE 7-10, ACI 318-11
Figure 3: NAU Engineering Building Architectural Plans
COST ESTIMATE
STAFFING
Table 1: Job titles and abbreviations
Table 3: Billing rates and total cost
Table 2: Tasks with hour allocations
PRELIMINARY DESIGN OPTIONS
Questions?
- Build Up
- Add new floors to existing building
- Build Out
- Expand footprint and attach to existing building
- Entirely New
- Entirely new footprint and design