The Internet belongs to everyone. Let’s keep it that way.

Protect Net Neutrality
Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Integrated Design Project (ECM506) 2014

Requirement for Final year students pursuing Civil Engineering in UiTM

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Integrated Design Project (ECM506) 2014

Integrated Design Project (ECM506)
Comparing ESTEEM and Manual Design
Continued-
Green Building Recommendation
ADVANTAGES OF LIGHTNING CONVERTER

PROTECT THE BUILDING
CONVERT THE LIGHTNING TO ELECTRICAL ENERGY
PROTECT THE ELECTRONIC DEVICES FROM LIGHTNING STRIKE
PROTECT THE PEOPLE IN THE BUILDING
INTRODUCTION
Infrastructures
Bill of Quantities
All the rate used in our BQ is based on the Jabatan Kerja Raya (JKR) Malaysia Schedule of Rates (S.O.R)

The bill of quantities produced is used as a benchmark to tender procurement process next

The BQ estimation is also for the client budgeting purposes
Q&A Session
This concludes our presentation for IDP (ECM506)

Thank You for listening and we bid your adieu
The contents for this presentation are:

Introduction
Comparison of structural and ESTEEM calculation
Green Building
Infrastructure
Bill of Quantities and Estimation
Team Member:

Abdullah Ali Said 2010253306
Mohd Faisal bin Ahmad Sabri 2010823632
Mohamad Azizzei bin Abdul Latib 2010257992
Muhammad Firdaus bin Abdul Halim 2010679378
The project proposed is a construction of 4 storey hotel at Lot 1234, Jalan Hospital, Sungai Buloh District, Selangor Darul Ehsan

The client of this project is Universiti Teknologi Mara (UiTM)

Cost of the project is about RM3 million

All the design is done by Consulting Civil & Structure engineers from HITECH ASSOCIATE

The architectural works is done by Azlina Abdullah Architect

The mechanical and electrical works is done by INFRA NETWORK CONSULTANTS

The QS consultant for this project will be JUB Ikatan Sepakat Sdn. Bhd.

Features of this hotel projects:

Have a seminar room (Ground floor)
Have a Surau (Musolla) for all the hotel guest
Have 51 hotel rooms
Have a lift passenger facility equipped with telephone lines for all the rooms in the hotel

The work duration for this project is 12 month

Total cost of the project is at RM3,004,009.95

There are 6 type of work that needs to be carried out, mainly on the C&S scope of work

The BQ produce does not include the scope of work from M&E engineers design.

6 type of works that in the C&S responsibility

Preliminaries works
Site clearance/earthworks
Piling works
Building works
Sewerage/drainage design works
Water reticulation system

There are 7 type of BQ produce to cover the 6 scope of work for C&S engineers, which are:

Preliminaries works
Site clearance/earthworks
Piling works
Building works
Sewerage/drainage design works
Water reticulation system
Contingency Sum
Total amount of project cost : Rm3,044,009.95
ADVANTAGES OF RAIN HARVESTING SYSTEM

EASY TO MAINTAIN
REDUCING WATER BILLS
CAN BE USED FOR SEVERAL NON-DRINKING PURPOSES
REDUCES FLOODS AND SOIL EROSION
ADVANTAGES OF WIND TURBINE

THE WIND IS FREE
WIND TURBINES DON'T PRODUCE ATMOSPHERIC EMISSIONS
WIND TURBINES ARE AVAILABLE IN A RANGE OF SIZES
CAN'T BE USED UP
ADVANTAGES OF STEEL FORMWORK

STRONG,DURABLE AND CAN BE REUSED MORE IN NUMBER
CAN BE INSTALLED AND DISMANTLED WITH GREATER EASE AND SPEED
DOES NOT ABSORB MOISTURE FROM CONCRETE
DOES NOT SHRINK OR WARP
ADVANTAGES OF GLASS WINDOW

HELP TO SAVE ENERGY
SAVE NATURAL RESOURCES
PROVIDE NATURAL LIGHT INTO BUILDINGS 
HAVE AESTHETICS VALUE
Slab comparison at GL (G-H/1-3)
Beam comparison at GL (2/B-C)
Column comparison at GL (G/5)
Pile comparison at G/5
Cut and Fill
Fill area amounting a total of 10,789.5 m3
Sewerage line
Consist of 5 proposed manhole each
at starting distance of 20m,60m, and 40m with a total of 200m long sewerage line to existing line
Water Supply
Proposed a suction tank of (3x3), with a peak flow = 1.08 L/s
Pressure head at existing pipeline is 130m and after design with 7 nodes each with distances of 65m,60m, and 7m with the last node at pressure head of 79.8m
Fire hydrant located as indicated of red mark, with pressure head of 81.164m from node 2.
Drainage
Taking into consideration of 5 years ARI with duration of 20 minutes storm flowing into an area of 0.67 hectares equivalent to 67.5 m2
Peak flow of 0.23 m3/s was to be estimated from storm
Proposed dimension for drain is (1x0.7) with 0.3m radius semi-circle at the bottom of drain