  1. Hi everyone. This is Susie wachowski.
  2. I am here to give you a brief update on the projects that were accomplished in Fy 21.
  3. The current status of the Fy 22 exhibit projects
  4. and what you can expect coming up in Fy 23
  5. Here is a dashboard um roll up that I developed
  6. that shows the status of the projects in Fy 21.
  7. As you can see, the majority of the projects were on target.
  8. Um that means they were either completed or um significant
  9. progress was made during the FY 21 fiscal year.
  10. Uh We had and we also had a couple of delays and um
  11. projects that were put on hold
  12. and those were primarily due to
  13. covid. So we had some staffing delays and we also had some supply chain issues.
  14. So um we have continued on
  15. Developing those projects in Fy 22.
  16. Here is a list of projects that we worked on in Fy 21. As you can see.
  17. The majority of the projects that we worked
  18. on were completed in that same fiscal year.
  19. Um and then we had a few that were carried over into Fy 22.
  20. Here's some reference photos to show you what we finished in Fy 21,
  21. we created signage for invasive round goby that
  22. go on boat ramps along the Missouri River.
  23. We developed the Discovery Trail
  24. and other trailhead signage of Baroque Woods. We
  25. updated the improving timber for your wildlife tabletop.
  26. We created a brand new Tree City usA tabletop that is designed to
  27. be taken to different outreach events and promote the Tree City usa program.
  28. Uh and then the big photo in the center is the eagle nest play area
  29. at Cape Nature Center and that was designed
  30. to give young visitors an immersive experience.
  31. Um so we can see what it feels like to be in an eagle nest.
  32. Um and through that experience they can learn about the
  33. habitat and the life cycle of bald eagles in Missouri.
  34. This is a chart of the design hours completed in fy 21
  35. broken down by project and it might be hard to read,
  36. but I just wanted to point out that you can
  37. see the majority of the projects we worked on,
  38. the majority of our time was spent working on the snake box,
  39. the pollinator table,
  40. um developing graphics for the fares and providing support for the fares,
  41. so that includes delivery takedown and actually running of the fair.
  42. And that is Fy 21 in an overview.
  43. Now,
  44. I want to talk to you about what FY22 projects are
  45. in the works and where we stand currently with those projects.
  46. Um as you can see the majority of the projects are
  47. on target for FY22 we have about 33% of the projects,
  48. um not started yet, but here we are, we're halfway through the fiscal year.
  49. So um those are still um in the works and we anticipate those being completed in Fy 22.
  50. We have had a few delays delayed projects.
  51. um but we,
  52. that's a very small amount and we anticipate
  53. moving forward with those projects as well.
  54. Here's a list of the projects were developing in Fy 22.
  55. I'm not going to read them to you all,
  56. but I just wanted to show you um what we have on the docket for the exhibit projects
  57. and here's a nice little visual that's supposed to outline um and give
  58. you a representation of the types of things that we're working on.
  59. So this top left picture is a mock up of the snake cart
  60. modular exhibit that we're fabricating.
  61. The top right is the bid package for Shoal Creek.
  62. We also have another bid package for the shepherd of the hills exhibits.
  63. And so both of those, we anticipate being completed,
  64. the contracts being awarded in fy 22
  65. work beginning in fy 23.
  66. We also have exhibit
  67. wayside finding um and a pollinator table that we are developing.
  68. Okay,
  69. taking a look at Fy 23 we are really honing in on those priority projects
  70. that in Fy 23 looking at Shoal Creek
  71. and shepherd the hills exhibit design contracts.
  72. Um and and that's where the majority of our exhibit efforts will be.
  73. Um We've also accepted these projects listed below and
  74. you can see we are going to try to tackle
  75. as many projects as we can um knowing that
  76. the majority of our focus will be on those two
  77. priority projects
  78. and that is a high level overview of what we accomplished in fy 21 where we are in fy 22
  79. what we can expect in fy 23.
  80. Thank you.