Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Con

No description
by

Desti Pratiwi

on 16 May 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Con

PERALATAN PEMBETONAN
(CONCRETE EQUIPMENT)

Pendahuluan
Hampir semua proyek konstruksi, beton dimanfaatkan sebagai bahan bangunan
PERALATAN PEMBETONAN
22-2011-129 Candra Ginanjar Sanusi
22-2011-156 Nina Dora B.
22-2011-159 Desti Santi Pratiwi
22-2011-167 Graatsiri Meta Arke

Beton merupakan campuran dari semen,
agregat kasar, agregat halus dan air namun
kadang kala campuran tersebut ditambahkan
bahan adiktif
Pekerjaan dalam pembuatan beton meliputi
a. Pengukuran berat setiap komponen beton.
b. Pencampuran bahan beton.
c. Pemindahan campuran beton.
d. Penempatan.
e. Konsolidasi.
f. Pengeringan
Peralatan yang biasa dipakai dalam proses pembuatan beton sampai beton tersebut ditempatkan adalah sebagai berikut
a. Peralatan pencampur beton ( concrete batching and mixing )
b. Peralatan pemindahan campuran beton.
c. Peralatan pengecoran
PEKERJAAN PEMBETONAN
Pengadukan Siap Tuang (Ready Mix)
Ready mix merupakan produksi dari sebuah pabrik pencampur (batching plan) kemudian diangkut dengan truk molen. Sistem pencampuran bisa melalui alat batchin plan, kemudian campuran beton yang sudah jadi sesuai dengan komposisi campuran beton yang dikehendaki dituangkan kedalam truk molen (system basah). Sistem pencampuran yang lain bahwa komponen beton ditakar di alat, setelah sesuai dengan komposisi beton rencana kemudian dituangkan kedalam truk molen (system kering) dan truk molen tadi selain sebagai pengangkut ke tujuan yang dikehendaki juga sebagai tempat pengadukan beton.
Pengadukan di tempat (site mix)
Pengadukan di tempat atau site mix lazimnya di tempat kita dikenal dengan 2 metode yaitu dengan pencampuran manual (tenaga manusia mengunakan skope, cangkul) dan yang kedua dengan mengunakan mesin molen.
Contoh Soal
Rumus yang digunakan
Produktivitas real concrete pump (m3/menit) = volume tiap segmen / waktu total.
Contoh Soal
Proyek Pembangunan Kantor PT.Trihamas Finance terletak di daerah Jakarta Selatan dengan Volume pengecoran lantai I sampai dengan II masing-masing = 99,9625 m3 dengan total waktu efektif = 132,095 menit dan waktu delay = 275 menit dalam 12 segmen, dan Volume pengecoran lantai III = 103,6375 m3 dengan total waktu efektif = 155,412 menit dan waktu delay = 294 menit dalam 12 segmen.Jika sekali memompa concrete pump dapat membawa 0,5 m3/menit. Berapakah nilai produktivitas real concrete pump pada pembangunan kantor di lantai 1 dan 2 dan berapa kali pemompaan concrete pump diakukan?
Solusi
Diketahui :

Volume pengecoran = 99,9625 m3
total waktu efektif = 132,095 menit
total waktu delay = 275 menit

Jawaban

waktu total = waktu efektif + waktu delay
= 132,095 + 275
= 407,095 menit

nilai produktivitas = volume pengecoran / waktu total
= 99,9625 / 407,095
= 0,2456
(m3/menit)
Lantai 1

total produktivitas Lantai 1 dan Lantai 2 = 2 x (0.2546)
= 0.5092 (m3/menit)
Jika concrete pump dapat membawa 0,5 m3/menit.
Maka pemompaan concrete pump dilakukan = 0.5092 / 0.5
= 1.0184 pemompaaan
Truck Mixer Concrete
Batching Concrete Plant
Concrete Mixer
Mobile Batching Plan
Concrete Vibrator
T
TERIMA KASIH
Concrete Pump
Concrete Pump Standar (Pompa standar)
Concrete Pump Long Boom (Pompa Long Boom)
Portable (Pompa Kodok)
Concrete Pump Mini
jenis pekerjaan peruntukan bangunan-bangunan rendah seperti rumah tinggal, ruko, mall dan lain-lain yang ketinggian bangunannya di bawah 20 meter dan pemakaian pipa beton di bawah 60 meter
jenis pekerjaan peruntukan untuk bangunan-bangunan tinggi seperti Perkantoran ruko lantai 5 s/d 7 lantai, yang ketinggian bangunanya diatas 20 meter
jenis pekerjaan untuk bangunan-bangunan seperti proyek Dam/bendungan, subway, pelabuhan, jety, pondasi PLN, pondasi menara telephone dan gang/ jalan sempit yang tidak bisa dilalaui mobil pribadi yang jangkauan horizontalnya / mendatar dari 120 meter samapai 170 meter
concrete pump dari jepang yaitu Truck mini Concrete Pump alat tersebut peruntukannya untuk bangunan-bangunan yang jalannya sempit dan ada portal yang hanya bisa dilalau mobil cold desel alat tersebut cocok untuk retail artinya untuk bangunan rumah tinggal ketinggian 1 s/d 2 lantai tetapi areanya terdapat di gang.
Pengertian
sebuah mesin/alat yang digunakan untuk menyalurkan adonan beton segar dari bawah ke tempat pengecoran atau tempat pengecoran yang letaknya sulit dijangkau oleh truck mixer
Keuntungan
1. Untuk saluran pipa hanya membutuhkan tempat yang kecil.
2. Beton bisa dipompa secara terus menerus.
3. Pompa dapat bergerak secara vertical dan horizontal.
4. Mobil concrete pump bisa ditempatkan dalam proyek besar atau kecil.
5. Concrete pump boom dapat mencapai bangunan konstruksi yang tinggi.
6. Memerlukan waktu yang cukup singkat dalam penggunaan dan pelaksanaannya
Bagian - Bagian Penting
A : Line Pump
B : Boom Pump
C : Trailer
B
A
C
Line Pump
Alat serba guna (pipa penyaluran beton saat memompa beton) yang mudah dibawa khusus digunakan untuk memompa beton tetapi tidak hanya digunakan memompa beton struktur tetapi juga untuk spesi semen atauadukan semen encer, beton basah, adukan kapur atau mortar
Boom Pump
Boom pump terdiri dari truk dan kerangka penyangga.Boom pump digunakanuntuk menuangkan beton dari slab pada saat cetakan beton siap untuk di cor pada bangunan tingkat tinggi, dengan volume yang besar dan untuk proyek industri
Trailer
Trailer adalah salah satu bagian dari concrete pump yang utama dan berfungsiuntuk membawa boom pump dan line pump
Jenis - Jenis
Produktivitas concrete pump adalah volume truk mixer dibagi dengan waktu pompa efektif atau ditulis dalam perumusan sebagai berikut:
Volume tiap segmen, yaitu volume dari tiap segmen pada tiap lantai.
Waktu efektif, yaitu waktu dimana concrete pump memompa beton cair untuk dialirkan ke segmen – segmen.
Waktu delay, yaitu waktu dimana concrete pump berhenti melakukan pemompaan.
Waktu delay ini bisa disebabkan bermacam – macam hal, seperti pemindahan pipa dari segmen 1 ke segmen 2, atau bisa juga pekerja yang bermalas – malasan.
Waktu total, yaitu jumlah dari waktu efektif dan waktu delay.