Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Make your likes visible on Facebook?

Connect your Facebook account to Prezi and let your likes appear on your timeline.
You can change this under Settings & Account at any time.

No, thanks

Copy of New Dar Al-Fouad Hospital Graduation Project Presentation

No description
by

Mohamed El-Faramawy

on 11 July 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Copy of New Dar Al-Fouad Hospital Graduation Project Presentation

Class Of 2014
Prepared By:
CEM Graduation Project
Project Description
Ahmed Maher Mohamed
Ahmed Sherif Sayed
Amal Khaled Nasr
Eman Osman Mohamed
Mohamed Abdelmoniem Abdelfattah

NEW DAR AL FOUAD HOSPITAL
The project is located at the intersection of Youssef Abbass Street & El Nasr Road , Nasr City , Cairo.

The building is composed of several zones :
• 3 Basements
• Ground Floor
• 8 floors
• Roof

Building Composition
The project is a five star hospital with capacity of 158 bed , and a medical tower of 220 physician clinics.
Contract Type & Project Participants
Approximate Cost = 374 million Egyptian Pounds
Contract Type : Unit Rate
Architect
Project Management :
Project Participants
Owner
Consultants
Contractor
The project is in its final stages of construction and just beginning in the finishing phase, as shown in the following site photos.

Current Project Progress
Project Location
Our scope will be the main building
Without External Works , Landscape & Electromechanical Works.

Work Breakdown Structure
WBS
Quantity Take-off ( QTO )
In the QTO task excel sheets were used to calculate the quantities , BLUE BEAM program was used to calculate the slabs areas off of PDF drawings.

The calculated quantities are as shown in the following tables.
Finishing
Works
Super
Structure
Sub
Structure
Parts
Floors
Concrete
Works
Project
Activities
CSI Divisions
Super
Structure
Sub
Structure
Floors
Activities
CSI Divisions
Cost Estimation
Costs were estimated for the quantities produced from the QTO of the Ground Floor.
Quality & Safety Plans
Method Statement
A Method Statement is a document which describes the procedure of the job to be completed & outlines the steps to be followed.
Chosen Topics
Earth work
Concrete work
Form work
Steel bridge
Quality Assurance & Quality Control
STEEL BRIDGE
Procedure:
Connecting main & sec. beams & lifting them up using the tower cranes.
Bracing is connected to the main girder.
Corrugated sheets are connected to sec beams and reinforced.
Pouring concrete.
Safety Hazards & How To Avoid:
1- Falling of components during lifting.
• Load must not be carried out over people or equipment.
• Ensure that the load weight is within the crane capacity.

2- Load sway during lifting.
• Only expert and well trained labors will be the responsible for lifting slings.
-Connections must be chcked & properly connected.
-All sections should be safe against all subjected stresses.
-Continusous supervision during the whole process.
Form work
Activity Listing & Coding System
Scheduling
-Milestones.
-Raft Execution Process.
PHASE 1
-Floor Parts Division.
Safety Plan
Quality Plan
1. DEFINITIONS
HSE:
Health, Safety & Environment

Safety Plan:
The Safety Plan represents the Contractor's plan for conducting safe work, preserving personnel, property and equipment.

Safety Policy:
It is the policy of the Contractor to establish throughout the entire organization the concept that people and property are our most important corporate assets.

2. OBJECTIVES
Is to minimize personnel injury and accidents for the Project.

3. PROCEDURE

1. Overseeing education of supervisors, employees and subcontractors regarding safety plans.

2. Monitoring safety performance.

3. Constant awareness meetings of good safety habits.

4. Providing employees with protective equipment..

5. Identification of potential hazards.

6. Conducting regular inspections of the safety procedures implementation.

4.PERSONS RESPONSIBLE FOR ACHIEVING HSE PLAN AND THEIR DUTIES.

1. PROJECT MANAGER

2. SAFETY OFFICER

3. SUPERVISORS

4. NURSE

5. INDIVIDUALS





GENERAL REQUIREMENTS:

1. TEMPORARY FACILITIES
2. TRAINING
3. FRIST AID
4. FALL PROTECTION
5. PROTECTIVE EQUIPMENT
Hazards & Precautions
1. Injury by sharp objects:
-Housekeeping must be done on daily basis, as well as nails, and any other sharp objects.

2. Electricity:
• All electrical panels should be provided with RCD or GFCI.
3. Person Falling
• Red card indicates that the scaffold is not safe.
• Ensure wearing HSE harness starting from 1.80 m high.

4.HAZARDOUS MATERIALS:
• Read the instructions on the hazardous materials carefully in order to avoid any accident.

Safety Report Templates
Procedure:

-Mounted in site except form of retaining walls which is pre formed.
-Leave one side open for rebar.
-Erection of supports.
-Plying .
-Pouring.
-Removing.
Safety Hazards & How To Avoid:

1-People falling off the bridge:
• Full body harness.
• A hand rail form work would be formed for the steel bridge.
2-Risk of puncture injury:
• Continuous site cleaning.
Quality Assurance

-Tightening Connections.
-Curing by oil.
-Cleaning of forms for re-use.

Quality control

-Withstand the weight of concrete .
-No mortar leakage or honeycomb.
-Checking the verticality.
Definitions:

Quality Plan :
-It’s a document that specifies the quality practices based on the general quality management principles.

Quality Assurance :
-It’s the system of actions and procedures to assure that the given products verify the set requirements.

Quality control :
-It’s the techniques and activities used for testing and inspection to examine and fulfill the stated requirements for quality.

People Responsible for Quality Plan:


Quality Manager.
Quality Assurance Engineer.
The Quality Control Engineer.
Technician .

Quality assurance

Back filling:
- The back filling will be from clean sand.
- Horizontal layers of 25 cm thickness
-Compaction to 95% of maximum dry density at the optimum moisture content.

Concrete Casting:
1. Pouring and compaction of concrete should be done in less 30 min after finishing mixing in normal conditions, and 20 min in hot conditions ( More than 30'C ).
2. Stop joints should be determined before starting concrete pouring.

Steel Structure works:
1-Align each part of the structure before making field connections.
2-Install high strength bolted joints.

Quality Control
Earth works:
Sand Cone Test:
- Determining Density of soil in place and moisture content.

1. Compressive strength of concrete:
-Test is performed in laboratory, on the samples taken during casting in the standard forms (Cubes).
Concrete Works:
2-Slump test
-Indicates if the concrete mix is wet or dry or in between and will define if it has the required workability or no.
Steel structures:
Steel Testing:
Using ultrasonic, magnetic particle, radiography, and visual inspection.
Resource Profiles
PHASE 2
Contracts
-Sequence of execution of activities.
Study Of Alternatives
1-Ready Mix Concrete Vs. Batch Plant Concrete.
2-Timber Shuttering VS. Steel Shuttering.
3- Concrete Placement Methods.

Ready Mix Concrete Vs. Batch Plant Concrete.
Effort

Price.
Less crowded
Avoid Labor burden
( Taxes, insurance, safety )
What-If Scenarios
Problem (1):
-Political Demonstrations.

Time Impact:
These demonstrations delayed project about a month during the construction phase

Cost analysis:
The contractor will not be responsible for any additional costs and will be granted a time extension.
While the employer will be responsible for one month's indirect cost which equals = 620,981 LE
Problem (2):
Quality Tests Failure:
The original duration of these activities was from (25-May) to ( 10-June) =15 days.
So if we double the crews of these activities it should be re-done in 8 days.
In addition to the removal time which will equal 10 days.
So the total repair duration will be = 18 days

Cost Analysis:
Assuming 7 workers 150 LE/day and we have 35 columns and productivity rate = 1 column / 2 days
The cost of removal of old columns (concrete only) for whole floor = (0.5*35*7*150)=18,375 LE
Cost of doubling the crews = 2*cost of columns activities - 2*cost of steel rebar - 1*cost of concrete = (2*627,888)-2*(4*94,500) -(4*39,200) = 342,976 LE
So the total cost of repair is = 342,976 + 18,375 = 361351 LE

Cash Flow & Over Draft
Cash out flow is the cumulative form of the costs incurred by the Contractor on the project on a monthly basis

Cost = Direct costs + Indirect costs

Direct cost

Indirect cost
Equal 8% from total budgeted cost
Monthly indirect cost = Indirect cost / Project duration

2-Cash inflow:
is the movement of money into or out of the project.

Importance of cash flow analysis:


Components of our analysis
1- Cash outflow
2- Cash inflow
3- Cash overdraft

Cash flow analysis



Retention percentage (R %)

The retention is a percentage of the project's price that is deducted from the Contract monthly to insure that the Contractor completes the construction and is returned to him after 12 months from the primary delivery time=10%
retention =0.1*contract price
Cash inflow is the series of payments from the Owner to the Contractor in response to the invoices issued by the later taking into account the following:
Addition of the markup (M %)
The markup is a percentage of the total budgeted cost that covers the contingency and the profit of the Contractor from the project = 8 %
Invoice price= Total Cost * (1 + M %)




1-Cash outflow:

Advance payment

is a percentage from the project's price. Its amount is given to him in the beginning of the project to facilitate the construction in the first few months when there is no payments from the Owner = 25%
Advance payment value = 0.15 * Project's price

Cash in= Invoice price – advanced payment-retention


Cash-in & Cash-out:
Overdraft
Cash over draft is the difference between the cash inflow and the cash outflow
Cash overdraft = Cash in – Cash out
there is a huge positive overdraft at the beginning of the project that can cover the negative overdraft if this money will not be used or invested elsewhere

Selected Topic 1
-It is a rating system for buildings that was designed to guide and distinguish high performance buildings that have less of an impact on the environment
-Rating systems are groups of requirements for projects that want to achieve LEED certification

(LEED) Leadership in Energy and Environmental Design
OUR HOSPITAL is a building design & construction.
There are five rating systems that address multiple project types:
-Typical certification thresholds
We try to achieve silver certificate for the project.
-Each rating system is made up of a combination of credit categories,The number of points the project earns determines the level of LEED Certification the project receives.
LEED BENEFITS
-Sustainable sites credits.
-Water efficiency credits.
-Energy & atmosphere credits.
-Materials & resources.
-Indoor environmental quality credits.
-Regional priority credits.
LEED CREDIT CATEGORIES
Choose an environmentally friendly site, utilizes sustainable and efficient designs.
 Some of its credit points are:
-Heat island effect – roof



-Site development - maximize open space

-Alternative transportation - bicycle storage and changing rooms
Sustainable sites credits
Promotes smarter use of water inside and out, to reduce potable water consumption.

Some credit points are:
Water efficient landscaping
Innovative wastewater technologies




Water efficiency credits
Promote better building energy performance through innovative strategies as using solar energy
Energy & atmosphere credits
Indoor environmental quality credits
Promote better indoor air quality and access to daylight and views, reduce incidence of asthma and respiratory allegry,as well as the impact on mental health as reducing depression&stress.
Improving the internal environment and reduce the effects of poor health by following green strategies .
-provide a completely smoke free.
-to minimize contaminants and vapours interior using paintings do not contain volatile organic compounds (VOCs) or contain very little of them.
-reduce the generation of airborne particles and outstanding atmosphere during the construction process.
-limit the entry of pollutant  from air by using filters to remove dust ana dirt from air before entring hospital.
Regional priority credits
Address regional environmental priorities for buildings in different geographic regions.
Four bonus points are available in this category.
Selected Topic 2 & 3
Project Planning
Dupming Analysis

Tower Cranes Conceptual Planning

• At mobilization stage and before starting Earth works, two Tower Cranes shall be fixed to serve whole area.

• We will consider some options for the tower cranes locations.
And that is the option (3rd option) which was already chosen in the project.
MOBILIZATION CONCEPTUAL PLANNING:

Temporary offices, facilities and Clinic are built before the earth works and foundation works commence, to accommodate site engineers, then offices are moved to basement after basement concrete works are done.

Storage:
• Some storage places shall be moved to the basements after its construction.
• Storage of steel only will be on site, otherwise storage will be in an area behind the site and transportation of material will be through trucks.
• Steel bars preparation will be carried out in external workshop, then transported and stored on site.

• Pouring Concrete:
Pouring Concrete will be through pumps of arm 42 m.

Option (1)
Using 5 trucks:
Cycle time=17 min.
Utilization factor for loader 1=15/17=0.88=88%
Utilization factor for Truck 1 to 5=17/17=100%
Utilization factor for loader 2=10/17=0.588=58.8%

Option (2)
Option (3)
Using 6 trucks:
Cycle time=18min.
Utilization factor for loader 1=18/18=100%
Utilization factor for Truck 1 to 6=17/18=0.944=94.44%
Utilization factor for loader 2=12/18=0.666=66.6%

Using 7 trucks
Cycle time=21min.
Utilization factor for loader 1=21/21=100%
Utilization factor for Truck 1 to 7=17/21=0.809=81%
Utilization factor for loader 2=14/21=0.666=66.6%

Conclusion
From the previous calculations it’s obvious that we either can use 5 or 6 trucks.
We chose to use 6 trucks because,
1. This will enable us to optimize the usage of the loaders while not affecting the efficiency of usage of trucks so much.
2. That’s better than using 7 trucks because using seven trucks will increase the cost while decreasing the efficiency of utilization of trucks without increasing the efficiency of loaders.
3. Hence truck capacity = 8 m3
so Productivity = (8/18)*60*8 = 213 m3/day

THANK YOU