Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Make your likes visible on Facebook?

Connect your Facebook account to Prezi and let your likes appear on your timeline.
You can change this under Settings & Account at any time.

No, thanks

SKENARIO PLAN OF

No description
by

Pradhita Winardi

on 4 July 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of SKENARIO PLAN OF

SKENARIO PLAN OF
DEVELOPMENT

Lokasi daerah Komplek Indramaju, Sumatra Selatan

Cekungan Sumatra Selatan: Sumatra Fault Zone

Conclusion
RESERVOIR DESCRIPTION
Mekanisme Pendorong Reservoir
Jumlah Sumur Pada Setiap Struktur :

Tujuan POD
Merencanakan skenario pengembangan lapangan yang memberikan hasil yang positif dari segi keekonomiannya pada prospek lapanhan yang akan dikembangkan.
Latar Belakang POD
Rencana pengembangan satu atau lebih lapangan minyak atau gas secara terpadu untuk mengembangkan atau memproduksi cadangan hidrokarbon secara optimal.
GEOLOGICAL FINDINGS AND REVIEWS
Geologi Regional
Cekungan Sumatra Selatan: after BEICIP 1985, Jaya Maju BPPKA 1997

1. Batuan Induk (Source Rock)
2. Kematangan (Maturity)
3. Batuan Reservoir (Reservoir
Rock)
4. Batuan Penutup (Seal Rock)
5. Waktu dan Migrasi

Petroleum Sistem


1940 : Struktur minyak dan gas Koang
1968 : Struktur gas Pasarbiru
1969 : Struktur minyak dan gas
Prabumoneng
1970 : Struktur gas Tisim
1999 : Struktur gas Kayangdewa


Eksplorasi Lapangan
1. Pada akhir tahun 2025 perkiraan kemampuan produksi dari komplek indramaju ini adalah 197,945MMSCF.
2. Dalam POD kami ini Harga Gas adalah merupakan factor yang paling dominan dalam perubahan nilai keuntungan.
3. Dalam POD ini diperoleh perolehan NPV sebesar = 198,480 MUS$ dan dengan ROR kami sebesar 176% dan Pay Out Time kami adalah 11 tahun.
4.Dengan melakukan workover, infill sumur dan juga pengadaan kompressor memakan biaya adalah sebesar MUS$ 15,355
5.Secara umum dari lapangan yang kami POD kan ini adalah ekonomis dan layak untuk dikembangkan.




Geologi Model
Model Sesal
Model Stratigrafi
Model Fasies
Model porositas
Model Net-To-Gross
Model Permeabilitas
Model Saturasi Air

Initial Condition
Struktur Pasarbiru Utara (PDW) dan Pasarbiru Selatan (PDS) merupakan reservoir penghasil gas
Pasar Biru
Karakteristik Batuan Reservoir Pasar Biru
Permeabilitas
Tekanan Kapiler
End Point
Karakteristik Fluida Struktur Pasar Biru
Jenis gas struktur Pasar Biru adalah wet gas.


Koang Selatan
Kondisi reservoar Koang merupakan saturated reservoir.
Karakteristik Batuan Reservoir Koang
Analisa Core
Porositas
Permeabilitas dan Tekanan Kapiler
Karakteristik Fluida Reservoir Struktur Koang
Didominasi oleh ekspansi fluida gas (Depletion Drive).

RESERVE AND PRODUCTION FORECAST
Development Scenario

Development Scenario
Skenario 1
Sumur Infill Sebanyak 6 Sumur
Work Over Sebanyak 15 Sumur
Skenario 2
Sumur Infill Sebanyak 3 Sumur
Work Over Sebanyak 4 Sumur
Pengadaan Kompresor

Perhitungan Cadangan di Tempat dengan Model Statik
Perhitungan Cadangan di Tempat dengan Model Dinamik
Untuk forecast produksi, menggunakan harga OGIP 2P Risk dari perhitungan Model Dinamik (100.46 BSCF untuk gas dan 12.59 mmbo untuk minyak)


Production Forecast
Scenario 1 : Rate Optimal Sebesar 25 mmscfd Selama 6 Tahun (2012-2018)
Scenario 2 : Rate Optimal Sebesar 11 mmscfd Selama 12 Tahun (2015-2023)
DRILLING
Di komplek Indramaju telah ditemukan beberapa struktur minyak dan gas, yaitu:

Struktur gas pasarbiru,
Struktur koang yang terdiri dari (koang utara dan koang selatan),
Struktur pemaat serta struktur gajah beringin
SURFACE FACILITIES
Lokasi
Peralatan Surface Facilities
Peralatan di kepala sumur
Well Head
Peralatan pengangkut
Flowline
Pipeline.
Peralatan pemisah
Dehydration Unit (DHU).

Skema Aliran Gas
Harga Alat
FIELD DEVELOPMENT SCENARIO
Tahun 2012
Pengembangan lapangan pada struktur pasarbiru dengan 6 buah sumur infil dan melakukan workover 25 sumur
Biaya drilling US$ 1,000,000
Biaya workover US$ 200,000/workover
Total biaya tahun 2012 US$ 9,000,000
Tahun 2013
Di struktur kong secenario pengembangan lapangan dengan infil sumur 4 dan melakukan workover selama 4 kali.
Total biaya tahun 2013 US$ 4,800,000

Tahun 2019
Di struktur pemaat dilakukan pengembangan lapangan dengan infil 2 sumur.
Total biaya tahun 2019 US$ 2,000,000

Tahun 2020
Di struktur Gajah beringin dilakukan pengembangan dengan infil 4 sumur.
Total biaya tahun 2020 US$ 4,000,000.
Kami juga mengansumsikan biaya capital sebesar 40%.

LOCAL CONTENT
Pada perencanaan pengembangan lapangan dibutuhkan tenaga ahli atau tenaga terampil untuk menunjang keberhasilan dari suatu perencanaan.
Penyewaan Alat Konstruksi
Penyewaan Kendaraan Sebagai Transportasi
Supply Sumber Daya Listrik (PLN)
Security System Dari Lingkungan Sekitar PEMDA
HEALTH,SAFE AND ENVIRONMENT
Menjaga keselamatan dan kesehatan pekerja serta masyarakat sekitar
Mengurangi potensi bahaya dalam lingkungan operasional dan sekitar
Melindungi lingkungan dari dampak pencemaran dan dampak negatif yang mungkin timbul


Tujuan
HSE Dalam Lapangan Kerja & Aplikasi HSE Dalam Pencegahan Pencemaran Lingkungan
Undang-undang yang mengatur adalah undang-undang No.1 Tahun 1970 tentang Keselamatan Kerja.
Pencegahan pencemaran lingkungan operasi pemboran lepas pantai adalah :
Dipasang tempat penampung lumpur dalam menghadapi Blow Out.
BOP dibuat aliran minyak dan lumpur ke kolam penampung.
Bila terjadi ceceran minyak di perairan, digunakan zat “Dispersar”.

Sumber Daya Manusia (SDM)
Fasilitas
DAFTAR JADWAL PROYEK DAN STRUKTUR PENGEMBANGAN
Upaya Pengelolaan Lingkungan (UKL) Dan Upaya Pemantauan Lingkungan (UPL)

Aplikasi HSE di bidang pemboran

Aplikasi HSE di bidang produksi

HSE didalam lapangan kerja

Aplikasi HSE di bidang pelindung
diri

Kejadian Berulang
Corporate Social Responsibility
Kejadian Tidak Berulang
COMMERCIAL
Hal yang dilakukan pada skenario POD ini adalah workover,infiil dan pengadaan kompressor
Economic Summary
Berikut ini data pada Ecconomic Sumarynya:


Discount Factor
Keekonomian proyect hingga economic limit
Indikator keekonomian
Skema Bagi Hasil

Asumsi- Ausumsi yang dilakukan untuk mencapai tabel diatas :
Pembagian keuntungan pemerintah –perusahaan
Pajak Pemerintah
FTP
Harga gas yang wajar,ekskalasi harga 4% pertahun
Biaya operasi produksi gas, ekskalasi 3% pertahun
Biaya operasi kondensat yang wajar
Metode Depresiasi
Berdasarkan asumsi- asumsi diatas maka didapat :

Sensitivity Analysis
Sensitivitas NPV
Sensitivitas ROR
Sensitivitas PIR