Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Time and Work

No description
by

EMPERIND

on 8 October 2018

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Time and Work

Ex 1:
15 men
can type
3240 pages
in
6 days
working
2 hours per
a day. how many men would be required to type
5400 pages
working
4 hours
per day for
3 days?
Sol:
P1 = 15
W1 = 3240
H = 2
D = 6
P2 = ? (x)
W2 = 5400
H = 2
D = 3
* Work is given .:. Then use formula 1
Ex II :
If 72 men can build a wall of
280 m length
, in
21 days
how many men could take
18 days
to build similar type of wall of length
100 m?

Sol:
P1 = 72
D1 = 21

W1 = 280

P2 = ? (x)
D2 = 18

W2 = 100

* Work is given then use formula 1
(iii)
39 persons
can repair a road in
12 days
working
5 hours
a day. in how many days will
30 persons
working
6 hours
a day complete the work.
Sol:
P1 = 39
D1 = 12

H1 = 5hours
P2 = 30

D2 = ? (x)

H2 = 6 hours
* work is not given, then use formula - 2
P1
H1
D1 =
P2

H2
D2
39 x 5 x 12 = 30 x
X
x 6
x = 13
(iv)
15 labours
complete a work in
10 days
working
6 hours
per day, if
18 labours
employed on that work and the work is to be completed in
5 days
then how many hours per day should the work be continued
Sol:
P1 = 15
;
D1 = 10

H1 = 6
P2 = 18
;
D2 = 5

H2 = ? (X)
* Working not given, then use formula 2
.:. P1 H1 D1 = P2 H2 D2
15 x 6 x 10
= 18 x X x 5

.:. x = 10
Type II
Based on efficiency
1. A is two times efficient then B =>
A B
5 Days 10 days
x
2x
x2
(ii) A is trice times efficient than B
=> A B
10 days 30 days
x
3x
(ii) A is four times efficient than B
=> A B
10 days 40 days
x
4 x X
4.

A is 50%
"more efficient" then
B
A
B
100%
150%
A
B
5.
A takes 50%
"more time"
than B
x
+
50% of x
For more complex problems
Ex:-
"A"
is twice as good
"B"
and
"B"

is twice as good as
"C"
if A and B can together finish a piece of work in
4 days
The
"C"
can do it by himself in:
Sol:
A B C
x days 2x 4x
* A + B completes a task in 4 days
.:. 1 day work => A + B
=
(ii)
A and B
together can do a work in
12 days.
B and C together do it in
15 days
. If A's efficiency is twice that of C,
Then The required for B alone to finish the work is.
let us take 1 day of work
B alone to finish the work alone is
.:. Substitute x value in Equation (i)
.:. B takes 20 Days
(iii) asha and Babu can do a job together in
7 days
Asha is 1 times as efficient as babu. Same job can be done by asha alone in?
let us take 1 day work
(iv) A can do a piece of work in
70 days
and B is
40% more efficient
than A. Then the number of days taken by B to do the same work is.
Sol :
A
B
70 days x days
140% 100 %
* B is more 40% Efficient Than
"A"
.:. B A

100% 140%
140% = 70 days
100% = x
.:. Remove (or) cancel percentages and cross multiply
140 x = 70 x 100
x = 50 days
(v) To complete a work.
A takes 50%
more time than B. if together they take
18 days
to complete work,
how much time shall B take to do it?
Sol:
A
B
x
+
50 of x
x
Type- III : Fraction of Work:-
Ex-(i) A can complete of a work in 4 days and B can complete of the work in 6 days.
in how many days can both A and B together complete the work?
Sol:
Ex (ii):
A can do of a piece of work in
5 days,
B can do of the same work in
9 days
and C can do of that work in 8 days. in how many day can all of them together do the work?
Sol:
(iii)
Sol:
(iii) A does work of a piece of work in
20 days
he calls B and they finish the remaining work in
3 days
how long B alone will take to do the whole work?
Sol:
(iv) A does
1/10 part of work
in
15 days
after that he completes the remaining work in
4 days
with the help of B
in how many days will A and B. Together do the same work?
Sol:
(v) A complete
2/3
of his work in
10 days.
Time he will take to complete
3/5
of the same work is .
Sol:
Step 1:
One day work done
Step 2:
Find Ratio
Step 3:
Find Share
1)
A can do work in
3 days.
B can do the same work in
2 days.
Both of them finish the work together and get
Rs.150

what is the share of A?
Sol:
2)
A and B under took to do a piece of work for
Rs. 4500
Alone could do it in
8 days
and B alone in
12 days
With the assistance of C they finished the work in
4 days
then C's share of money is:
Sol:
3. Three persons undertake to complete a piece of work for
1200 Rs.
the first person can complete the work in
8 days
second person in
12 days.
and third person in
16 days
They complete the work with the help of a fourth person in
3 days.
What does the fourth person get?
Sol:
4.

A, B, C
completed work costing
Rs.1800
A worked for
6 days
, B for
4 days
and C for
9 days,
If their daily wages are in the ratio of
5 : 6 : 4
, how much amount will be received by A?
Sol:
Daily wages
=>
5 : 6 : 4
6 x 4
4 x 6
9 x 4
A : B : C = 5 : 4 : 6
120
5.
a man and a boy received
Rs.800
as wages for
5 days
for the work they did together. The man's efficiency in the work was three times that of the boy.
what are the daily wages of the boy?
Sol:
M + B = 5 days = 800
the man efficiency
is trice than the Boy
In term of days
in term of work
x : 3x
5 : 15
3 : 1
M : B
x3
6.
If
5 Men
(or)
7 women
can Earn
Rs.5250
Per day. How would
7 men
and
13 women
Earn per day?
Sol:
5 men = 5250
1 men = 1050
7 men = 1050 x 7
= 7350
1 men =
7 women = 5250
1 women =
1 women = 750
13 women = 750 x 13
= 9750
17 , 100
7
.
2 men
and
1 women
together can complete a piece of work in
14 days,
while
4 women
and
2 men
together can do it in
8 days.
If a man gets
Rs.600
per day, how much should a woman get per day?
Sol:
SHORT CUT
8.

A, B, C
together Earn
Rs.150
per day while A and C together Earn Rs.94 and B & C together Earn Rs.76 The daily Earning of 'C' is ?
Sol:
1.
A and B
together can complete a work in
3 days
they started but after
2 days
B left the work. If the work is completed after
2 more
days.
B
alone could do the work in how many days?
sol:
Normal Method:
2.
Ajay can do a piece of work in
25 days
and sanjay can finish it in
20 days.
They work together for
5 days
and then ajay goes away. In how many days will sanjay finish the remaining work?
Sol:
Short cut :2
3.
A and B
can do a piece of work in
60 days
and
75 days
respectively. Both begin together but after a certain time
A
leaves off. In such case,
B
finishes the remaining work in
30 days.
After how many days did A leave?
short cut :1
Normal method
Short cut : 2
4.
A
can complete a piece of work in
40 days
. He starts working, but having some other engagement leaves after
5 days.
Thereafter,
B
completes this work in
21 days.

How many days would A and B take to complete this work working together?
Sol:
Normal method
Short cut I:
short cut: II
1.
Ajay and sunil together can complete a piece of work in
10 days.
sunil and sanjay in
15 days
and sanjay and Ajay in
20 days,
They worked together for
6 days,
and then ajay leaves. Sunil and sanjay worked together for
4 more days
and sunil leaves.
How long will sanjay take to complete the work?
Sol:
2.
A, B and C can do piece of work in
16, 32 and 48
days respectively. They all begin together. A work continuously till it is finished,
C leaves
the work
2 days
before its completion. and B leaves the work the work 1 day before its completion,
In what time is the work finished?
Sol:
3.
A and B
can finish a job in
10 days,
while
B and C
can do it in
18 days.

A
started the job and worked for
5 days
and left the job . Then
B
worked for
10 days
and remaining job is finished by
C
in
15 days.

In how many days
C
alone have finished whole job?
Sol:
x
.:.
.:.
=
4
2
1
15
10 days
8
=>
(A +B) x
39
120
3
10
4.
A can complete a piece of work in
40 days
.
He starts working, but having some other engagement leaves after 5 days. Thereafter
B

completes this work in
21 days
.
How many days would A and B take to complete this work working together?
sol:
Normal Method
Ex 1:
15 men
can type
3240 pages
in
6 days
working
2 hours per
a day. how many men would be required to type
5400 pages
working
4 hours
per day for
3 days?
Ex II :
If 72 men can build a wall of
280 m length
, in
21 days
how many men could take
18 days
to build similar type of wall of length
100 m?