Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

Make your likes visible on Facebook?

Connect your Facebook account to Prezi and let your likes appear on your timeline.
You can change this under Settings & Account at any time.

No, thanks

Walsworth Bridge

No description
by

Pablo Nistal Iglesias

on 10 October 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of Walsworth Bridge

Walsworth Bridge
Project Documents
• Approximate location of statutory undertakers plant

• Record of Mitigation Measures (permanent) Rev 1

• Record of Mitigation Measures (temporary) Rev 1

• BoQ Preamble and Item Coverage

• BoQ

• Manifest

• Drawing Carriageway and Kerb Levels
Project Documents
• Drawing GA (1 and 2)

• Drawing RF (1,2 and 3)

• Drawing Pedestrian Management

• Drawing TM

• CDM2 Pre-Construction Information Pack

• Walsworth Contract

• WT Programme

• Work Photos
Health and Safety Measures
Quality Measures
Environment Measures
The aim of the project is to reinforce the brick arch while maintaining the outer parapet and arch.
Location
Demolition
Partial demolition of existing brick wall and small demolition works.

Use of hydraulic hammer attached to an excavator and also manual pneumatic hammers.
Earth-moving
Earthworks including excavation, deposition and compaction of soil in the work site, and geotechnical site investigation.

Preliminary Works
• Work Offices

• Centring, Props, Temporary Platforms

• Traffic Management

• River Diversion

Contractor Company
Taking into account the budget of the project (around 300000£), a small local contractor company would be able to handle it.
Analysis of demolition and earth-moving activities
Existing Arch Prior to Work
In this case, Amey is the one chosen with the help of Chevron (traffic safety and management) and Mouchel (environmental impact).
Work Offices
Erection, servicing and dismantling of portable offices, stores and workshops.

Resources:
Portable offices = 1
Stores and workshops =1

Budget:
66198,57£
Schedule: One day

Centring, Props, Temporary Platforms
Placement of the temporary structures necessary for the implementation of the work.
Resources: Machinery (trucks, cranes...), labor and structural components (props, beams...).
Budget:
9950£
Schedule: Four days

Traffic Management
Taking measures for traffic and pedestrian diversion during the construction. A different company takes care of this part.
Resources:
Budget:
36181,18£
Schedule: 82 days
River Diversion
Installation of a temporary dam and piping in the River Purwell beneath the bridge.

Resources: Sandbags and pipes
Budget:
1200£
Schedule: Four days

Demolition
Earth-moving
Budget
Demolition
Earth-moving
Partial demolition of individual structures (such as brick wall, curbs, concrete posts...)
Total Budget:
11599.92£
Total Budget:
26422.60£
Excavation, disposal and compaction of materials, and geotechnical site investigation.
Schedule
Demolition:
Site Clearance/Demolition 2 days (01.03.11-02.03.11)
Site Clearance/Demolition 2 days (05.04.11-06.04.11)

Earth-moving:
Trial Holes 1: 2 days (01.03.11-02.03.11)
Excavation (saddle south): 3 days (07.03.11-09.03.11)
Trial Holes 2: 1 day (04.04.11-04.04.11)
Excavation (saddle north): 3 day (09.04.11-12.04.11)
Analysis of Concrete Structures
Analysis of Paving Activities
Concrete Structures
Paving Activities
Execution of the pavement, what includes curbs, foot-ways, paved areas, traffic signs, road markings and road restraint systems.
Use of trucks, motor graders, a paver, compactors and auxiliary equipment.

Schedule:
Budget:
Budget of the structural concrete:
61.657, 58£
Budget of bridge expansion joints and sealing of the gaps:
754, 00£

Schedule:
Weight of steel per cubic meter of concrete in:

North cantilever: 270kg/m3

South cantilever: 400kg/m3

Saddle: 65 kg/m3
Budget:
25834.77£
Pavement
Curbs, foot-ways and paved areas
Traffic signs and road markings
Road Restraint systems
Total budget
14883.8£
1655.8£
4022.79£
5272.38£
25834.77£
Brickwork, block work, stonework
Waterproofing
Electricity and telecommunication
Drainage and service ducts
Removing the pointing in existing brickwork and re-point them or removing existing brickwork and replace it with matching bricks.
Budget:
2837.70£
Health and Safety
General
Health and Safety plan and periodical inspections
Working practices
Construction waste treatment
Workers equipment (bituminous joint sealant and epoxy mortar)
Public safety
Protection of pedestrian and vehicular traffic
Quality measures
1. Introduction and documents
2. Preliminary Works
3. Demolition and earth-works
4. Concrete structures and pavement
5. Health and Safety, Quality and Environment
6. Extra activities
Machinery used: Track mixer, concrete pumps and auxiliary cranes.
Check geometry
Paving process
Compaction
Reinstall traffic signs
Road restraint systems
Tests performed on material used during the work
Environment Measures
Permanent effects
Temporary effects
Noise
Dust, emissions and odors
Flora and fauna
Ground
Water
Material use
Local community
Uncertain waterproofing system in previous arch.
Applied to the concrete structure
Budget:
Works should not be carried out:
• 15 meters where lines are carried on steel towers
• 9 meters where the lines are carried on wood poles

Works related to the raising or lowering of the level of existing services.
Budget:
Athletic Complex
María Ruiz, Amaia Ayerdi, Ainhoa Arribas, Moisés Álvarez, Pablo Nistal