Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

ECU Mendenhall Report Presentation

No description
by

Davis Kane Architects

on 3 October 2018

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of ECU Mendenhall Report Presentation

MASTER WORK LIST Full Build Out
"F" & "G"
Fire Safety Improvements
ECU Mendenhall Comprehensive Renovation (Programming)
Master Work List EBC
Utilization of the
Existing Building Code
Design Team's Recommended Path
Do you want to comply with the
2018 NC Building Code
?
YES
NO
Life Safety Improvements
Accessibility
Deferred Maintenance
Designer Recommendations
Building Function
Cost Implications
This facility Assessment and Programming Report should be utilized by all stakeholders to assist in reaching a consensus on the best path forward
Schematic Design to commence no later than October 1st to stay on schedule
Construction Document Review by SCO - June/July 2019
Construction Completion - March 2021
Schedule
Identify Phasing restrictions
Budget:
Per the OC-25, updated 2/21/2018:
Estimated Construction Cost is $15,176,178
Total Estimated Project Cost is $18,154,000
The fundamental conclusion is that all of the repairs and program elements cannot be implemented with the available funding
Do you want to comply
with the
2018 NC Building Code
(without acknowledging the Existing Building Code Exceptions)?
YES
Fire Safety Improvements
Life Safety Improvements
Accessibility
Deferred Maintenance
Owner Request
Building Function
3 Strategies For Mendenhall Renovation
Thermal
HVAC
Electrical
IT
Thermal
Water
HVAC
Electrical
IT
Life Safety
Area of Alteration
Programming
Owner Priorities
Let's prioritize together to fit your budget
Owner Requested
Designer Recommendations
1. Renovate the entire building satisfying all of the known code and building deficiencies and complete all of the interior upfits. This includes all new building systems. This program far exceeds the available budget.

2. Renovate the building in the “core” and unassignable areas only. This includes all new building systems except within the upfit areas. This scheme is very close to being within budget.

3. Renovate the eastern (1987) portion of the building. This includes all new building systems except with limited partial system installation in the western (1070) portion of the building. This scheme can be within budget but has shortcomings.

Water
Area Served
Equal Distance