Loading presentation...

Present Remotely

Send the link below via email or IM

Copy

Present to your audience

Start remote presentation

  • Invited audience members will follow you as you navigate and present
  • People invited to a presentation do not need a Prezi account
  • This link expires 10 minutes after you close the presentation
  • A maximum of 30 users can follow your presentation
  • Learn more about this feature in our knowledge base article

Do you really want to delete this prezi?

Neither you, nor the coeditors you shared it with will be able to recover it again.

DeleteCancel

PMP Calculations

No description
by

Hugo McLeod

on 5 April 2014

Comments (0)

Please log in to add your comment.

Report abuse

Transcript of PMP Calculations

PMP Calculation Links
AC
Actual Cost
BAC
Budget at Completion
PV
Planned Value
X
EV
Earned Value
CV
Cost Variance
-
SV
Schedule Variance
-
BAC
Budget at Completion
EV
Earned Value
EV
Earned Value
AC
Actual Cost
PV
Planned Value
X
BAC
Budget at Completion
CPI
Cost Performance Index
EV
Earned Value
/
AC
Actual Cost
SPI
Schedule Performance Index
EV
Earned Value
/
PV
Planned Value
X
BAC
Budget at Completion
EAC
Estimate at Completion
BETC
Bottom-up Estimate to Complete
Original Estimate not valid
AC
Actual Cost
+
BETC
Bottom-up Estimate to Complete
CPI will stay the same for Project
Current CPI is abnormal
Project has to meet a deadline
EAC- I
EAC- II
EAC- III
EAC- IV
BAC
Budget at Completion
/
CPI
Cost Performance Index
EV
Earned Value
/
AC
Actual Cost
AC
Actual Cost
+
(
)
ETC
Estimate to Complete
EAC
Estimate at Completion
Original Estimate not valid
AC
Actual Cost
+
BETC
Bottom-up Estimate to Complete
CPI will stay the same for Project
Current CPI is abnormal
Project has to meet a deadline
EAC- I
EAC- II
EAC- III
EAC- IV
BAC
Budget at Completion
/
CPI
Cost Performance Index
EV
Earned Value
/
AC
Actual Cost
AC
Actual Cost
+
(
)
-
AC
Actual Cost
TCPI
To-Complete Performance Index
TCPI I
BAC is Valid
TCPI II
BAC is no longer valid
BAC
Budget at Completion
-
EV
Earned Value
/
BAC
Budget at Completion
-
AC
Actual Cost
BAC
Budget at Completion
-
EV
Earned Value
/
EAC
Estimate at Completion
Original Estimate not valid
AC
Actual Cost
+
BETC
Bottom-up Estimate to Complete
CPI will stay the same for Project
Current CPI is abnormal
Project has to meet a deadline
EAC- I
EAC- II
EAC- III
EAC- IV
BAC
Budget at Completion
/
CPI
Cost Performance Index
EV
Earned Value
/
AC
Actual Cost
AC
Actual Cost
+
(
)
-
AC
Actual Cost
BAC
Budget at Completion
-
EV
Earned Value
AC
Actual Cost
+
[( )/( )]
BAC
Budget at Completion
-
EV
Earned Value
CPI
Cost Performance Index
EV
Earned Value
/
AC
Actual Cost
x
SPI
Schedule Performance Index
EV
Earned Value
/
PV
Planned Value
X
BAC
Budget at Completion
x
Good Luck !!